Activity
From 01 Jan 2025 to 10 Jan 2025
10 Jan 2025
- 21:53 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- 21:53 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- test use shared version
- 21:52 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- test
- 21:49 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #885 (Closed): get requirement and create specification Doc. [Taping])
- create specification Doc. R1
- 21:44 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
- sick leave
- 21:44 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
- Sick Leave
- 21:43 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
- sick leave
- 21:43 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
- Sick Leave
- 18:00 PT NIPPON KONPO INDONESIA 4.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Import file Additional for ImportDeliveryInstruction
- 17:58 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
- Separate menus for WH and PD
- 16:50 PORITE CORPORATION 8.00 hours (Project progress work #768 (Closed): [Colding] Front-End Web dashboard application PHP)
- Web Dashboard (45%)
- 16:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Prepare to install the application.
- 16:40 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Prepare to install the application.
09 Jan 2025
- 17:05 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Finish Import file DELIVERY_INSTRUCTION_INDO, DELIVERY_INSTRUCTION
- 16:58 PORITE CORPORATION 8.00 hours (Project progress work #768 (Closed): [Colding] Front-End Web dashboard application PHP)
- Web Dashboard (40%)
- 16:43 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Prepare to install the application.
- 16:43 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Prepare to install the application.
08 Jan 2025
- 18:31 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Finish Import file Shipping INS
- 17:00 PORITE CORPORATION 8.00 hours (Project progress work #768 (Closed): [Colding] Front-End Web dashboard application PHP)
- Web Dashboard (35%)
- 16:27 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Fix bug Tablet, Handy, Web for system installation.
- 16:27 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- 14:47 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #877 (Closed): [Coding] Test and fixed function with ISEWAN)
- On site testing and fix with asuto and isewan#4.
07 Jan 2025
- 18:26 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Create table for import file schedule and Stored Procedure
- 17:59 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Fix bug for system installation.
- 17:59 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Fix bug for system installation.
- 17:03 PORITE CORPORATION 8.00 hours (Project progress work #768 (Closed): [Colding] Front-End Web dashboard application PHP)
- Web Dashboard (30%)
- 16:37 PORITE CORPORATION 8.00 hours (Project progress work #768 (Closed): [Colding] Front-End Web dashboard application PHP)
- Web Dashboard (15%)
06 Jan 2025
- 20:04 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Test and prepare for system installation.
- 20:03 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Test and prepare for system installation.
- 17:54 PT NIPPON KONPO INDONESIA 1.00 hour (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Internal meeting with K.Ryo and team
- 17:53 PT NIPPON KONPO INDONESIA 6.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Set up system to clound and set up master data https://tom-demo-01.proen.app.ruk-com.cloud/nki/pegasus/
- 16:39 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 2.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- Add UI detail of outbound 2/2
- 16:39 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- Add UI detail of outbound 1/2
- 16:38 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- [Task] TBFST Add UI Detail page 4/4
- 16:38 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- [Task] TBFST Add UI Detail page 3/4
- 16:38 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- [Task] TBFST Add UI Detail page 2/4
- 16:37 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- [Task] TBFST Add UI Detail page 1/4
- 16:37 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- TBFST add menu navigate UI.
- 16:31 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
- 14:32 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 4.00 hours (Project progress work #690 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
- 14:31 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 4.00 hours (Project progress work #506 (Closed): [Coding] Warehouse management system Web app PHP)
- Working process for TBFSH - create simulate tables from ERP - create View tables from simulate table - import data to...
- 13:14 TOMAS TECH CO., LTD. 4.00 hours (Sales support #863 (Closed): Training)
- MOXA about converter Nport/Mgete
- 13:13 TOMAS TECH CO., LTD. 4.00 hours (Sales support #863 (Closed): Training)
- Aluminum profile design program - misumi
05 Jan 2025
- 20:44 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
- Fix permission for admin 70%
04 Jan 2025
- 17:10 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
- Modify Web (100%)
- 16:29 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
- Production outbound, Outbound manual
- 16:29 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
- Production outbound, Outbound manual
- 16:07 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
- 16:07 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (03/01) Support i-Reporter
- 14:52 THAI METALTECH CO., LTD. 4.00 hours (Project progress work #605 (Closed): [Coding] Warehouse management system Web app PHP Phase02)
- Improve error catch report for import file.
03 Jan 2025
- 17:25 NKT NIPPON KONPO (THAILAND) CO., LTD 4.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Read the document and install the database, then deploy the code to the website on the cloud.
- 17:20 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
- Develop Test Scenarios document 80%
- 17:19 THAI METALTECH CO., LTD. 8.00 hours (Project progress work #605 (Closed): [Coding] Warehouse management system Web app PHP Phase02)
- Change Label lotsize and format add quatity, total_boxs
- 16:53 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
- Modify Web (95%)
- 16:33 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
- Work outbound
- 16:33 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
- Work outbound
- 16:28 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #877 (Closed): [Coding] Test and fixed function with ISEWAN)
- Testing and fixed issues after test with ISEWAN#4.
- 08:29 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (27/12)Support i-Reporter
Also available in: Atom