14:50 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #847 (Closed): PICS - Support handy terminal)
Testing and fix picking #4. Taweesak Prumvised
14:50 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #847 (Closed): PICS - Support handy terminal)
Testing and fix picking #3. Taweesak Prumvised
14:50 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #847 (Closed): PICS - Support handy terminal)
Testing and fix picking #2. Taweesak Prumvised
14:50 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #847 (Closed): PICS - Support handy terminal)
Testing and fix picking #1. Taweesak Prumvised
14:49 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #847 (Closed): PICS - Support handy terminal)
Inspection packing function #3. Taweesak Prumvised

14 Dec 2024

17:14 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
Modify Web (45%) Worawit Khantamool
17:12 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
Develop User Master import Nattaporn Chaiya
16:44 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Q-Gate Process Priroj Neamjarn
16:44 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Q-Gate Process Priroj Neamjarn
16:08 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 2.00 hours (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
dashboard Thiraporn Amornsirinukorh
15:53 EBISU FOODS CO., LTD. 2.00 hours (Project progress work #761 (Closed): WMS Pegasus & API linkage)
new api working Thiraporn Amornsirinukorh
15:51 EBISU FOODS CO., LTD. 4.00 hours (Project progress work #761 (Closed): WMS Pegasus & API linkage)
On-site meeting with client Thiraporn Amornsirinukorh
08:20 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
Support i-Reporter Panthita Roekdee

13 Dec 2024

17:16 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
Modify Web (40%) Worawit Khantamool
17:16 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
Modify Web (33%) Worawit Khantamool
17:16 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
Develop Labelsetting Master, Modify import User Credential Master Nattaporn Chaiya
16:44 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
Fix Bug Page Purchase Instructions Ronnagon Kongsuwan
16:43 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
Fix Bug Page Purchase Instructions Ronnagon Kongsuwan
16:43 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
Chage Requied Outbound production set outmin stock and remote test on site. Ronnagon Kongsuwan
16:43 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
Modify Page Purchase Instructions Ronnagon Kongsuwan
16:42 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
Modify Page Purchase Instructions Ronnagon Kongsuwan
16:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Q-Gate Process Priroj Neamjarn
16:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Q-Gate Process Priroj Neamjarn
15:20 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
Support i-Reporter Panthita Roekdee

12 Dec 2024

16:44 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Coding Q-Gate Priroj Neamjarn
16:44 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Coding Q-Gate Priroj Neamjarn
16:41 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
Develop import Process Master, Ng reason Master, create Labelsetting Master Nattaporn Chaiya
13:42 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
Support i-Reporter, Create i-Reporter form,Meeting Panthita Roekdee
11:23 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
On site (1/1) Worawit Khantamool

11 Dec 2024

21:52 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
fix: check user & machine on Process Soraya Norasing
21:45 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
Soraya Norasing
21:51 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
update system & support user Soraya Norasing
21:50 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
support user at yamato(Practical trial) Soraya Norasing
21:48 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
modify HT for new requirement (category filter, inbound FG default location fix), check error and fix : change locati... Soraya Norasing
21:43 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
Personal leave Soraya Norasing
21:43 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
take annual leave Soraya Norasing
17:16 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
Finish create modal Authority, finish import name master Nattaporn Chaiya
17:16 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
Support i-Reporter, Create i-Reporter form Panthita Roekdee
16:28 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
coding Q-Gate process Priroj Neamjarn
16:28 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
coding Q-Gate process Priroj Neamjarn

10 Dec 2024

17:26 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
Develop Process Master Nattaporn Chaiya
16:58 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
Modify Web (26%) Worawit Khantamool
16:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
Support i-Reporter, Create i-Reporter form,Meeting Panthita Roekdee
16:39 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 4.00 hours (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
dashboard Thiraporn Amornsirinukorh
16:39 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 4.00 hours (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
dashboard Thiraporn Amornsirinukorh
16:38 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #506 (Closed): [Coding] Warehouse management system Web app PHP)
Site survey / spec R1 Thiraporn Amornsirinukorh
16:22 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
create stored procedure, create trigger Priroj Neamjarn
16:21 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
create stored procedure, create trigger Priroj Neamjarn
11:04 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #847 (Closed): PICS - Support handy terminal)
Inspection packing function #2. Taweesak Prumvised
11:03 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #847 (Closed): PICS - Support handy terminal)
Inspection packing function #1. Taweesak Prumvised

09 Dec 2024

17:29 MINEBEA ACCESSSOLUTIONS THAI LTD. 5.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
Develop Auth for login Nattaporn Chaiya
17:28 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
Support i-Reporter, Create i-Reporter form Panthita Roekdee
17:28 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 3.00 hours (Project progress work #743 (Closed): Development EDI system)
Install EDI on cloud server Nattaporn Chaiya
17:01 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #777 (Closed): [Colding] Front-End Web dashboard application PHP)
Modify Web (7%) Worawit Khantamool
16:39 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
create stored procedure, trigger Priroj Neamjarn
16:39 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
create stored procedure, trigger Priroj Neamjarn

06 Dec 2024

21:52 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
Support i-Reporter, Meeting with customer Panthita Roekdee
17:29 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #781 (Closed): [Colding] Web application PHP)
Create DB for new department DC, PO, PA Nattaporn Chaiya
16:59 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #833 (In Progress): [TMS-Calling] Web development.)
Web theme migration (4/10) Worawit Khantamool
08:27 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #833 (In Progress): [TMS-Calling] Web development.)
Web theme migration (3/10) Worawit Khantamool
16:52 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
meeting and IV program with Keyence Konlawat Saechee
16:48 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
Checking finally before finishing projec Konlawat Saechee
16:51 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
Developed and completed fixes for Purchase Instructions, including insert, edit, and delete functions, and added temp... Ronnagon Kongsuwan
16:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #524 (New): Konlawat Saechee Taking Day off January-December 2024)
Take leave Konlawat Saechee
16:29 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
wiring,assemble Konlawat Saechee
16:26 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Internal test case Priroj Neamjarn
16:25 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Internal test case Priroj Neamjarn
 

Also available in: Atom