Activity
From 16 Nov 2024 to 25 Nov 2024
25 Nov 2024
- 22:14 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- 17:19 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #762 (Closed): Fix web problems)
- Stocktaking Identify display issues
- 16:56 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add upload image function on mobile app.
- 16:38 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #810 (Closed): Coding BackEnd New Menu)
- Coding backend miter capacity
- 16:37 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #810 (Closed): Coding BackEnd New Menu)
- Fix Frontend Overall Chart
- 16:19 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- PC Schedule Outer, Schedule Vanning
- 16:18 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- PC Schedule Receive, Schedule Staging, Schedule Inner
- 14:32 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
24 Nov 2024
- 18:06 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 11/15
- 18:05 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 10/15
- 18:05 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 9/15
- 18:04 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 8/15
- 18:04 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 7/15
- 18:04 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 6/15
22 Nov 2024
- 16:57 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add task modification page.
- 16:46 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. 8.00 hours (Project progress work #752 (Closed): Install HT Software and Server Onsite.)
- Make HT Software Manual.
- 16:32 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #807 (Closed): Coding Frontend New Menu )
- Coding Frontend Overall Chart
- 16:32 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- -PC Schedule Receive, Schedule Staging, Schedule Inner
- 16:32 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- -PC Schedule Receive, Schedule Staging, Schedule Inner
- 16:24 MINEBEA ACCESSSOLUTIONS THAI LTD. 7.00 hours (Project progress work #762 (Closed): Fix web problems)
- Create new record schedule outbound
- 16:05 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 1.00 hour (Project progress work #506 (Closed): [Coding] Warehouse management system Web app PHP)
- Create work directory for pegasus
- 16:04 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 1.00 hour (Project progress work #506 (Closed): [Coding] Warehouse management system Web app PHP)
- Meeting / Brief / Spec with K.Nack and K.Pai
- 11:30 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
- 08:31 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 08:25 TOMAS TECH CO., LTD. 8.00 hours (Sales support #809 (Closed): METALEX 2024)
- Booth setup
21 Nov 2024
- 17:26 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 1.00 hour (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
- bug fix / preparation for test
- 17:26 EBISU FOODS CO., LTD. 2.00 hours (Project progress work #761 (Closed): WMS Pegasus & API linkage)
- Schedule inbound / outbound
- 16:55 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add caller and test task fucntion.
- 16:50 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Edit Tag Receive label
- 16:50 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Edit Tag Receive label
- 16:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- Install HT Software.
- 16:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #807 (Closed): Coding Frontend New Menu )
- Coding Frontend Overall Chart
- 16:26 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 3.00 hours (Project progress work #743 (Closed): Development EDI system)
- Check DB on server customer and install EDI system on server test
- 15:01 HAMADEN MEXICO S.A.DE C.V 8.00 hours (Project progress work #808 (Closed): Test connecting PLC with BTA500)
- support k.pai
- 14:59 HAMADEN MEXICO S.A.DE C.V 4.00 hours (Project progress work #808 (Closed): Test connecting PLC with BTA500)
- support k.pai
- 14:54 HAMADEN MEXICO S.A.DE C.V 4.00 hours (Project progress work #808 (Closed): Test connecting PLC with BTA500)
- support k.pai test connecting PLC
- 14:53 HAMADEN MEXICO S.A.DE C.V 8.00 hours (Project progress work #808 (Closed): Test connecting PLC with BTA500)
- support k.pai test connecting PLC
- 14:58 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer
- 14:56 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer
- 10:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI)
- programming of demo
- 10:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI)
- programming of demo
- 10:38 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support Installation
- 10:38 AH BRAKE (THAILAND) CO., LTD. 9.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support Installation
- 10:37 AH BRAKE (THAILAND) CO., LTD. 10.50 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support Installation
- 10:11 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
- 09:28 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #762 (Closed): Fix web problems)
- Create new record schedule inbound
20 Nov 2024
- 17:14 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add caller function on mobile application.
- 16:59 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- Install HT Software.
- 16:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #807 (Closed): Coding Frontend New Menu )
- Coding Frontend Bekido Chart and Fix Frontend Electric Summary
- 16:32 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Vanning Finish Case (Tablet)
- 16:31 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Vanning Finish Case (Tablet)
- 15:06 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #760 (Closed): Production Control Budomari Information board (Display))
- Display 1 & Display 2 Query fixed
- 14:06 EBISU FOODS CO., LTD. 3.00 hours (Project progress work #761 (Closed): WMS Pegasus & API linkage)
- bug fix and testing
- 14:04 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
- 13:58 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
- test / fixed / config / add new response for api
- 09:56 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Project progress work #762 (Closed): Fix web problems)
- Create new record Departmant master data
19 Nov 2024
- 23:22 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Fix bugs before training and adjust code based on the client's requested changes.
- 23:17 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Developed Page Purchase Instructions and stock card current stock.
- 23:15 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Install website and build database server
- 23:14 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- trainning user
- 17:05 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- Install HT Software.
- 10:09 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- Install HT Software.
- 16:52 TOMAS TECH CO., LTD. 2.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Edit web socket.
- 16:51 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 6.00 hours (Project progress work #590 (Closed): [Coding] Warehouse management system handyterminal Java)
- Test and fixed after test.
- 16:44 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- Trial day 1
- 16:42 YAMATO ELECTRIC (THAILAND) CO., LTD. 2.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- Pick up the printer from office
- 16:41 MINEBEA ACCESSSOLUTIONS THAI LTD. 2.00 hours (Project progress work #753 (Closed): Process Management System [Design & Get requirements])
- 16:38 A.N.I. LOGISTICS, LTD. 4.00 hours (Parent project #708 (Closed): IKD System - Migrate AS400 to Pegasus at PCB site)
- Preparing function list document
- 16:37 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #756 (Closed): [Colding] Web dashboard application PHP)
- Coding Frontend Bekido Chart
- 16:19 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Vanning Finish Case
- 16:19 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Vanning Finish Case
- 12:23 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Project progress work #762 (Closed): Fix web problems)
- Modify Edit function User Master
- 08:05 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
18 Nov 2024
- 21:53 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Program installation
- 21:52 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Program installation
- 21:51 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Program installation
- 21:51 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Program installation
- 21:51 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Program installation
- 21:51 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Program installation
- 21:52 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
- Access point installation
- 01:18 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
- Support installation
- 00:08 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
- Support installation
- 21:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Develop program function NG and Troubleshooting
- 21:49 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Develop program function NG and Troubleshooting
- 17:19 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #762 (Closed): Fix web problems)
- Create new record and edit and search view User Master, User Credential
- 17:16 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add separate condition of web socket 1/2.
- 17:13 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 4.00 hours (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
- bug fixed
- 17:12 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 5.00 hours (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
- Inbound Schedule Detail > ng_reason
- 17:12 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 1.00 hour (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
- Internal test with K.Pai 4/5
- 17:11 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 1.00 hour (Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs )
- Internal test with K.Pai 3/5
- 17:10 EBISU FOODS CO., LTD. 4.00 hours (Project progress work #761 (Closed): WMS Pegasus & API linkage)
- Testing Receipts/Issues
- 16:35 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Setup Finish Case
- 16:35 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Setup Finish Case
- 16:33 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #807 (Closed): Coding Frontend New Menu )
- Coding Frontend Meter Capacity
- 16:33 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #763 (New): ANDON DASHBOARD DESIGN AND PROGRAMMING)
- Program and Dashboard Development
- 16:32 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #763 (New): ANDON DASHBOARD DESIGN AND PROGRAMMING)
- Program and Dashboard Development
- 16:31 FTS AUTOMOTIVE (THAILAND) CO.,LTD 8.00 hours (Project progress work #764 (New): FTP DATA LOGGING)
- Program PLC and HMI Development
- 15:53 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
- 01:18 OTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #645 (Closed): [ Installation&On-site support ] Power meter monitoring system for OTICS)
- installation Rasberry Pi
- 01:17 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- Wiring cabinet
- 01:17 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- Wiring cabinet
- 01:16 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- Support installation
- 01:16 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- Support installation
- 01:15 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- test camera
- 00:32 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- Wiring cabinet
- 00:32 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- Wiring cabinet
- 00:32 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #802 (Closed): [Area3] Camera control system)
- Wiring cabinet
- 01:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:13 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:12 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:11 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:10 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:10 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Wiring cabinet
- 01:12 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
- Test FTP at site
- 01:11 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
- Test FTP
- 00:47 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
- Test FTP
- 01:08 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support installation
- 01:08 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support installation
- 00:45 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support installation
- 00:45 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support installation
- 00:45 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support installation
- 00:45 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support installation
- 00:45 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Support installation
- 00:44 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Wiring cabinet
- 00:39 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Wiring cabinet
- 00:28 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Wiring cabinet
- 00:28 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Wiring cabinet
- 00:12 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Wiring cabinet
- 00:11 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Wiring cabinet
- 00:43 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #806 (New): Estimate cost)
- Estimate cost for AH brake CNC monitering
- 00:43 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #806 (New): Estimate cost)
- Estimate cost for AH brake CNC monitering
- 00:38 KEYENCE (THAILAND) CO., LTD. 8.00 hours (Project progress work #805 (Closed): PR Electrical part for demo No.259)
- PR Electrical part list
- 00:15 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #696 (Closed): Electrical Diagram)
- Site Survey
- 00:10 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #696 (Closed): Electrical Diagram)
- Drawing EE
- 00:14 TOMAS TECH CO., LTD. 8.00 hours (Sales support #798 (New): Site survey customer for new project)
- Site Survey Copland and Thai asahi denso
17 Nov 2024
- 23:58 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #804 (Closed): NTN concept panel)
- Estimate cost
- 23:58 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #804 (Closed): NTN concept panel)
- Drawing EE
- 23:56 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #700 (Closed): PR Electrical part )
- Make PO
- 23:55 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #696 (Closed): Electrical Diagram)
- Drawing EE
- 23:55 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #696 (Closed): Electrical Diagram)
- Drawing EE
- 23:44 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
- Support installation
- 22:54 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
- Site Survey
- 23:44 YAMATO ELECTRIC (THAILAND) CO., LTD. 7.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- 23:43 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- 23:43 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- Final SIT
- 23:43 YAMATO ELECTRIC (THAILAND) CO., LTD. 4.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- 23:43 OTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #645 (Closed): [ Installation&On-site support ] Power meter monitoring system for OTICS)
- installation Cooling unit
- 23:42 A.N.I. LOGISTICS, LTD. 2.00 hours (Parent project #708 (Closed): IKD System - Migrate AS400 to Pegasus at PCB site)
- 23:40 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 2.00 hours (Project progress work #803 (Closed): [Documentation] Get requirements of project)
- UAT at online
- 23:36 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #753 (Closed): Process Management System [Design & Get requirements])
- Update spec version 2
- 23:36 MINEBEA ACCESSSOLUTIONS THAI LTD. 3.00 hours (Project progress work #753 (Closed): Process Management System [Design & Get requirements])
- 23:35 A.N.I. LOGISTICS, LTD. 1.00 hour (Parent project #712 (Closed): EKD System phase4 for ANI Ayuthaya)
- Meeting about new concept of topology due to use an old L3 manage switch
- 23:31 TOMAS TECH CO., LTD. 1.00 hour (Project progress work #646 (Closed): WDT and smartwatch demo project)
- Assign work regarding MAST demo to khun Puk
- 23:28 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.260
- 23:28 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.252
- 23:11 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.259
- 23:10 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.259
- 23:10 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.259
- 23:25 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
- [Task] LAT - STEP - Installation 5/5
- 23:25 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
- [Task] LAT - STEP - Installation 4/5
- 23:25 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
- [Task] LAT - STEP - Installation 3/5
- 23:25 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
- [Task] LAT - STEP - Installation 2/5
- 23:24 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
- [Task] LAT - STEP - Installation 1/5
- 23:23 ASIAN STANLEY. INTERNATIONAL LIMITED. 1.00 hour (Project progress work #754 (Closed): [Design] Design and consult)
- Meeting about application design of handy working in an offline mode
- 23:23 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 5/15
- 23:23 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 4/15
- 23:22 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 3/15
- 23:22 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 2/15
- 23:22 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
- [Task] LAT - PICS - Installation 1/15
- 23:21 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 4.00 hours (Project progress work #623 (In Progress): [Installation] Install Raspi and TV monitor)
- 23:13 TOMAS TECH CO., LTD. 8.00 hours (Sales support #711 (Closed): LAZADA Barcode reader systems)
- Estimate cost
- 22:48 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #697 (Closed): PR Electrical part )
- PR Electrical part list
- 21:26 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #697 (Closed): PR Electrical part )
- PR Electrical part list
- 21:26 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #697 (Closed): PR Electrical part )
- PR Electrical part list
- 22:47 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
- Wiring cabinet
- 22:43 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
- PR Electrical part list
- 22:43 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
- PR Electrical part list
- 22:42 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
- PR Electrical part list
- 22:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #699 (Closed): Electrical Diagram)
- Meeting at site
- 22:32 OTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #799 (Closed): Check Power meter)
- Check Power meter
- 21:18 TOMAS TECH CO., LTD. 8.00 hours (Sales support #798 (New): Site survey customer for new project)
- site survey at HAVI
- 21:01 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #523 (New): Phatthadon Inthachot Taking Day off January-December 2024)
- Personal Leave
- 21:00 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #523 (New): Phatthadon Inthachot Taking Day off January-December 2024)
- Sick leave
- 18:14 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:12 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:10 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:10 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:09 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:09 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:08 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
16 Nov 2024
- 22:17 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- 22:16 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- trainning user
- 22:15 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- Install program on handy, set up handy
- 22:11 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- modify HT function wirebond & api
- 22:11 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- modify HT function wirebond
- 17:42 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:42 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 TOMAS TECH CO., LTD. 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:38 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 10.50 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 15:48 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 11.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 15:48 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 15:46 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 6.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 15:46 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 9.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 15:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 10.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:45 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 9.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 11.50 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:43 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 12.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:41 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 12.50 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:32 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 12.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 11.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:30 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 14:30 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 11.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 13:52 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 12.00 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation
- 13:46 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 10.50 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support Installation Addon monitoring
- 17:27 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- Safety training
- 15:47 AH BRAKE (THAILAND) CO., LTD. 4.50 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- On-site support installation
- 14:52 AH BRAKE (THAILAND) CO., LTD. 9.50 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- On-site support installation
- 14:51 AH BRAKE (THAILAND) CO., LTD. 9.50 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- On-site support installation
- 14:48 AH BRAKE (THAILAND) CO., LTD. 12.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- On-site support installation
- 14:48 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
- On-site support installation
- 17:23 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3D Printing Assembly
- 17:15 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #762 (Closed): Fix web problems)
- Create new record Master Data item
- 17:03 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #756 (Closed): [Colding] Web dashboard application PHP)
- Coding backend Production Monitoring Gantt Chart
- 16:52 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Check HT Software.
- 16:44 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Setup Finish Case (Handy)
- 16:44 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Setup Finish Case (Handy)
- 16:18 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:18 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:18 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:18 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:15 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Assembly hardware and wiring
- 16:13 HAMADEN MEXICO S.A.DE C.V 3.00 hours (Project progress work #694 (Closed): [Development] Software design and development)
- Edit users manual and fixed bugs some function.
- 16:12 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 5.00 hours (Project progress work #590 (Closed): [Coding] Warehouse management system handyterminal Java)
- Fixed stocktaking and location.
- 14:38 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 14:38 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 14:28 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 13:39 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 13:38 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 13:36 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 13:34 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 13:32 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 13:30 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 13:28 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
- Packing Process Hardwar assembly internal
- 09:57 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
Also available in: Atom