Project

General

Profile

Activity

From 13 Oct 2024 to 22 Oct 2024

22 Oct 2024

16:44 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Login process
tomorrow
-Outer Packing Process
-Inner Packing Process (new customer request)
Priroj Neamjarn
14:13 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(22/10)Meeting with customer (Hayakawa)(11.00-12.00), Support i-Reporter NTPT Panthita Roekdee
14:02 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #752 (In Progress): Install HT Software and Server Onsite.
Install HT Software and Server Onsite. Kamol Anekchatnuntakool
14:01 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #752 (Closed): Install HT Software and Server Onsite.
Install HT Software and Server Onsite. Kamol Anekchatnuntakool

21 Oct 2024

16:32 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Inner Packing process
-Login process
tomorrow
-Login process
-Outer Packing Process
Priroj Neamjarn
08:26 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
Priroj Neamjarn
11:42 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (55 %)
KDPP5000 (55 %)
KDPP...
Kamol Anekchatnuntakool
00:11 NIPPON KONPO (THAILAND) CO., LTD. Project progress work #751 (Closed): Design and get requirements
3 sub projects
- WMS
- Transport system
- Tracking system
Kittisak Isarapongporn

17 Oct 2024

16:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (55 %)
KDPP5000 (55 %)
KDPP...
Kamol Anekchatnuntakool
16:17 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Inner Packing process
-Travel to the office
tomorrow
-Inner Packing process
-Login process
Priroj Neamjarn
15:53 THAI METALTECH CO., LTD. Project progress work #750 (Closed): Fixed function Web Pegasus after training.
After the training, testing and solving any issues encountered during real worksite. Ronnagon Kongsuwan
08:06 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(17/06)Meeting with customer (Sumitomo)., Support i-Reporter NTPT Panthita Roekdee

16 Oct 2024

16:56 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (55 %)
KDPP5000 (55 %)
KDPP...
Kamol Anekchatnuntakool
16:35 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(16/10)Support i-Reporter NTPT Panthita Roekdee
16:31 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
Priroj Neamjarn

15 Oct 2024

16:36 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
Priroj Neamjarn
13:42 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(15/10)Support i-Reporter NTPT Panthita Roekdee
09:48 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Parent project #724 (In Progress): [PJ******] JTEKT Production IoT & Infrastructure IoT dashboard
Ryo Nozaki

14 Oct 2024

21:58 TOMAS TECH CO., LTD. Project progress work #748 (Closed): ALPHA Design inspection station
- 3D Design inspection station
- 2D Drawing
- Estimate cost
- Meeting
- Survey
Konlawat Saechee
21:52 ADVICS MANUFACTURING (THAILAND) CO., LTD. Problem-Bug #716 (Confirmation request): PLC data clear error
Konlawat Saechee
21:51 TOMAS TECH CO., LTD. Project progress work #678 (Confirmation request): LEGO
Konlawat Saechee
 

Also available in: Atom