- 16:56 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (55 %)
KDPP5000 (55 %)
KDPP... - 16:35 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (16/10)Support i-Reporter NTPT
- 16:31 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
15 Oct 2024
- 16:36 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process - 13:42 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (15/10)Support i-Reporter NTPT
- 09:48 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Parent project #724 (In Progress): [PJ******] JTEKT Production IoT & Infrastructure IoT dashboard
14 Oct 2024
- 21:58 TOMAS TECH CO., LTD. Project progress work #748 (Closed): ALPHA Design inspection station
- - 3D Design inspection station
- 2D Drawing
- Estimate cost
- Meeting
- Survey - 21:52 ADVICS MANUFACTURING (THAILAND) CO., LTD. Problem-Bug #716 (Confirmation request): PLC data clear error
- 21:51 TOMAS TECH CO., LTD. Project progress work #678 (Confirmation request): LEGO
12 Oct 2024
- 11:59 TOMAS TECH CO., LTD. Parent project #726 (In Progress): [PJ*****] Mobile project for NFC smart card and calling system for mobile
11 Oct 2024
- 17:25 YAMATO ELECTRIC (THAILAND) CO., LTD. Project progress work #594 (In Progress): [Coding] Warehouse management system handyterminal PHP web
- 16:50 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (11/10)Support i-Reporter NTPT, Create i-Reporter form(Hayakawa)
- 16:48 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (55 %)
KDPP5000 (55 %)
% ... - 16:33 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
- [[Inner Packing process]]
tomorrow
-Inner Packing process
-Login process - 14:57 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #747 (In Progress): Testing Modify Pegasus to Pegasus2
- 14:57 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #747 (Closed): Testing Modify Pegasus to Pegasus2
- 1. Transition Pegasus website from Pegasus1 to Pegasus2 design.
2. Test all existing functionalities after migration... - 14:37 THAI METALTECH CO., LTD. Project progress work #650 (Confirmation request): [Coding] Warehouse management system Web App PHP Pegasus Phase1
- 12:49 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #707 (Confirmation request): Modify Webpegasus.
10 Oct 2024
- 17:01 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (55 %)
KDPP5000 (25 %)
% ... - 16:41 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Inner Packing process
tomorrow
-Inner Packing process - 16:39 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING
- DASH BOARD DESIGN AND PROGRAMMING
- 08:33 TOMAS TECH CO., LTD. Sales support #745 (Closed): Pokayoke Inspection System-TOYOTA BOSHOKU SIAM METAL
- -3D design
-2D Drawing
-Estimate cost
09 Oct 2024
- 16:54 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (55 %)
% Done 30% - 16:44 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #494 (In Progress): STEP - Version upgrade development support
- 16:30 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Inner Packing process
tomorrow
-Inner Packing process - 13:11 TOMAS TECH CO., LTD. Sales support #744 (Closed): ATSUMITEC-Inspection station
- - site survey
- Meeting
- 3D Design
- 2D Drawing
- Estimate cost part ME - 11:45 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #743 (Closed): Development EDI system
- - Linkage Data API
- Main page, Login
- Print / Issued Tag page
- Print / Issued Tag (Special Tag) page
... - 11:42 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #742 (Closed): Documents and Database EDI system
- API - Documents
Design - information
08 Oct 2024
- 17:02 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (45 %)
% Done 28% - 16:41 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Receive process
tomorrow
-Inner Packing process - 07:04 THAI METALTECH CO., LTD. Project progress work #741 (In Progress): Fixed function after training.
07 Oct 2024
- 18:05 THAI METALTECH CO., LTD. Project progress work #741 (Closed): Fixed function after training.
- - SDI function
- Pokayoke function.
- Update users manual. - 17:03 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (75 %)
KDPP2000 (35 %)
% Done 26% - 16:39 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4