Activity
From 03 Oct 2024 to 12 Oct 2024
12 Oct 2024
- 08:42 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Meeting api and add UI.
11 Oct 2024
- 17:17 YAMATO ELECTRIC (THAILAND) CO., LTD. 6.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Developed and completed Production Delivery fontend and created table mrpregister for use in page stock_purchase_inst...
- 14:46 YAMATO ELECTRIC (THAILAND) CO., LTD. 4.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Modify and completed Import Production Schedule Delivery Csv.
- 16:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter NTPT, Create i-Reporter form(Hayakawa)
- 16:49 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (10/10)Support i-Reporter NTPT, Create i-Reporter form(Hayakawa)
- 16:48 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (09/10)Support i-Reporter NTPT, Create i-Reporter form(Hayakawa)
- 16:48 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (08/10)Support i-Reporter NTPT, Create i-Reporter form(Hayakawa)
- 16:48 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (07/10)Support i-Reporter NTPT, Create i-Reporter form
- 16:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Develop UI Interface 1/1.
- 16:48 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 16:34 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Inner Packing process
- 16:33 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Inner Packing process
- 16:30 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 4.00 hours (Project progress work #733 (Closed): Design and documentation)
- Update and revise spec revision 2
- 16:22 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- 16:21 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- Meeting with K.Pairoj about explain the additional requirements
- 15:02 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. 2.00 hours (Project progress work #747 (Closed): Testing Modify Pegasus to Pegasus2)
- Created example test files for CSV import (PO and Delivery types), along with initial testing of website and database...
- 14:48 THAI METALTECH CO., LTD. 4.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
- Testing and Fixed Production Lotsize Web backend storeproduce function cut material and cut stock.
- 14:42 THAI METALTECH CO., LTD. 4.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
- Present all process production Sdi function schedule, cut stock and modify with client tmc.
- 14:39 THAI METALTECH CO., LTD. 4.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
- Modify Production Lotsize Test and fixed lotsize with haddy.
- 14:22 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 5.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop Linkage Data API function create and document
- 00:53 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- Inbound rework/rework ng
- 00:52 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- Inbound rework/rework ng : modify api & android (100%)
- 00:51 TOMAS TECH CO., LTD. 3.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- internal meeting with K.nack about ASI project , Internal meeting with k.pum about php
- 00:49 A.N.I. LOGISTICS, LTD. 5.00 hours (Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java)
- check data : outer data is incorrect, edit query api
10 Oct 2024
- 23:55 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- 23:55 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- 23:54 TOMAS TECH CO., LTD. 2.00 hours (Project progress work #671 (In Progress): [Meeting] Interview and other)
- Meeting about calling system and smartwatch system source code
- 23:50 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 4.00 hours (Project progress work #658 (Closed): Documents and design)
- 21:58 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop Linkage Data API function create and document
- 17:03 THAI METALTECH CO., LTD. 4.00 hours (Project progress work #741 (Closed): Fixed function after training.)
- Test and fixed lotsize.
- 17:01 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 16:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:44 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:43 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:43 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:43 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:43 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:42 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:42 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:41 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:41 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:41 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:41 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:41 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #746 (Closed): ANDON DASH BOARD DESIGN AND PROGRAMMING)
- 16:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Inner Packing process
- 16:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Inner Packing process
- 08:56 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 26/36
- 08:55 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 25/36
- 08:55 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 24/36
- 08:55 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 23/36
- 08:54 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 22/36
- 08:54 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 21/36
- 08:53 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 20/36
- 08:53 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 19/36
- 08:52 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 18/36
- 08:52 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 17/36
- 08:51 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 16/36
- 08:51 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 15/36
- 08:50 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
- [Task] LAT - REPO - Conversion and Documents Creation 14/36
- 08:49 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 26/36
- 08:48 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 25/36
- 08:48 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 24/36
- 08:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 23/36
- 08:43 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 22/36
- 08:42 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 21/36
- 08:42 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 20/36
- 08:41 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 19/36
- 08:41 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 18/36
- 08:40 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 17/36
- 08:40 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 16/36
- 08:39 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 15/36
- 08:39 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
- [Task] LAT - CYLC - Conversion and Documents Creation 14/36
- 08:37 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 18/30
- 08:37 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 17/30
- 08:36 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 16/30
- 08:36 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 15/30
- 08:35 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 14/30
- 08:34 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 13/30
- 08:34 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 12/30
- 08:33 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 11/30
- 08:33 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 10/30
- 08:32 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 9/30
- 08:31 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 8/30
- 08:31 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 7/30
- 08:30 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 6/30
- 08:33 TOMAS TECH CO., LTD. 8.00 hours (Sales support #745 (Closed): Pokayoke Inspection System-TOYOTA BOSHOKU SIAM METAL)
- 3D design
- 08:28 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer
- 08:27 TOMAS TECH CO., LTD. 4.00 hours (Sales support #744 (Closed): ATSUMITEC-Inspection station )
- 3D design
- 08:26 TOMAS TECH CO., LTD. 8.00 hours (Sales support #744 (Closed): ATSUMITEC-Inspection station )
- 3D design
09 Oct 2024
- 16:54 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 16:52 THAI METALTECH CO., LTD. 5.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
- Modify and Use function cut stock fifo in trigger and web pegasus.
- 16:50 THAI METALTECH CO., LTD. 3.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
- Meeting with the user to fix functions after training, testing SDI functionality, and gathering additional requirements.
- 16:49 THAI METALTECH CO., LTD. 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
- Created and completed Function Stored procedure Cut Stock by fifo.
- 16:45 THAI METALTECH CO., LTD. 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
- Testing and fixed outbound SDI Function with handy.
- 16:47 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop layout system and login page
- 16:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 5/30
- 16:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 4/30
- 16:46 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 3/30
- 16:46 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 2/30
- 16:46 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
- [Task] LAT - STEP - Conversion and Documents Creation 1/30
- 16:45 TOMAS TECH CO., LTD. 6.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add UI Screen all pages.
- 16:44 THAI METALTECH CO., LTD. 2.00 hours (Project progress work #741 (Closed): Fixed function after training.)
- Add scan QRCode of schedule SDI page.
- 16:31 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Inner Packing process
- 16:30 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Inner Packing process
- 00:35 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- 1. Installation & onsite at NTPT, 2. meeting with NTMT about modify HT input, 3. meeting with K.sakda ASI about reque...
- 00:31 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #674 (Closed): [Installation]Process Control System phase2)
- support usert PLCC about data machine wrong, support user CHIP classify process cannot gen lot no. and gen lot no. wrong
08 Oct 2024
- 21:05 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #658 (Closed): Documents and design)
- Update spec revision 4
- 21:04 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Pick the USB dongle and check the Asprova functions about part and machine lock/unlock
- 21:03 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- 17:20 THAI METALTECH CO., LTD. 8.00 hours (Project progress work #741 (Closed): Fixed function after training.)
- Testing and fixed outbound SDI Function.
- 17:02 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 16:42 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
- 16:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
07 Oct 2024
- 18:06 THAI METALTECH CO., LTD. 3.00 hours (Project progress work #741 (Closed): Fixed function after training.)
- Test SDI Function.
- 18:03 TOMAS TECH CO., LTD. 5.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Created project and initial UI.
- 17:03 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 16:39 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
- 16:39 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
06 Oct 2024
- 22:24 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #733 (Closed): Design and documentation)
- 22:22 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- 22:22 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- 22:22 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- 22:21 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- 22:18 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- Meeting about describe and assign to K.Pairoj
- 22:20 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- 22:20 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Setting and check Asprova
- 22:20 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Setting and check Asprova
- 21:05 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer
- 21:05 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer
- 21:04 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer
05 Oct 2024
- 17:37 HAMADEN MEXICO S.A.DE C.V 6.00 hours (Project progress work #694 (Closed): [Development] Software design and development)
- Add setup information of user manual.
- 17:36 TOMAS TECH CO., LTD. 2.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Daily meeting / Review spec document meeting.
- 17:07 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Developed and completed Page Production Schedule Type Injection And Press,Created New Page Outbound Material Build Pr...
- 17:04 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Developed and completed Import Production Schedule Type Injection And Type Press (backend)
- 16:59 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 16:32 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Create i-Reporter form
- 16:30 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
- 16:30 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
04 Oct 2024
- 22:56 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- Inbound rework/rework ng : create & test api
- 22:56 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- Inbound rework/rework ng : modify function on android
- 22:54 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- meeting with K.oil about issue i-reporter, meeting with customer ASI about schedule project, support user ASI about c...
- 22:51 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- Meeting Asprova system at NTPT, Support user ASI about printer
- 17:08 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 17:03 HAMADEN MEXICO S.A.DE C.V 4.00 hours (Project progress work #694 (Closed): [Development] Software design and development)
- Edit users manual.
- 16:54 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Create i-Reporter form
- 16:41 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #734 (Closed): PICS - Handy Terminal - Test confirmation )
- [Task] LAT - PICS - Handy Terminal - Test confirmation 5/5
- 16:41 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #734 (Closed): PICS - Handy Terminal - Test confirmation )
- [Task] LAT - PICS - Handy Terminal - Test confirmation 4/5
- 16:40 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #734 (Closed): PICS - Handy Terminal - Test confirmation )
- [Task] LAT - PICS - Handy Terminal - Test confirmation 3/5
- 16:40 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #734 (Closed): PICS - Handy Terminal - Test confirmation )
- [Task] LAT - PICS - Handy Terminal - Test confirmation 2/5
- 16:40 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #734 (Closed): PICS - Handy Terminal - Test confirmation )
- [Task] LAT - PICS - Handy Terminal - Test confirmation 1/5
- 16:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
- 16:40 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Receive process
- 16:33 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Learning i-Reporter.
- 08:24 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 10.50 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
- Support installation server pc rack
03 Oct 2024
- 16:57 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
- Make Document HT Software.
- 16:56 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- -Receive process
- 16:55 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- -Receive process
- 16:29 HAMADEN MEXICO S.A.DE C.V 4.00 hours (Project progress work #694 (Closed): [Development] Software design and development)
- Add users manual1/1.
- 16:29 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Developed and completed Modify fontend page Inbound production schedule, Inbound production schedule detail and creat...
- 16:27 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Developed and completed Modify page Bom and Crusher ratio page and trigger production use material cut fifo
- 16:25 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Developed and completed schedule production type injection and type press in page schedule import
- 16:28 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Daily meeting / Review spec document.
- 13:29 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Create i-Reporter form
- 13:26 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (02/10)Support i-Reporter NTPT(meeting with K.So and NTPT teams), Create i-Reporter form