Activity
From 24 Sep 2024 to 03 Oct 2024
03 Oct 2024
- 17:36 HAMADEN MEXICO S.A.DE C.V Project progress work #694 (Confirmation request): [Development] Software design and development
- 17:08 THAI METALTECH CO., LTD. Project progress work #604 (Confirmation request): [Coding] Warehouse management system handyterminal Java Phase01
- 17:08 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. Project progress work #590 (Confirmation request): [Coding] Warehouse management system handyterminal Java
- 16:57 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (50 %)
% Done 16% - 16:55 A.N.I. LOGISTICS, LTD. Project progress work #739 (In Progress): [Development] CKD process system phase4
- today
-Receive process
tomorrow
-Receive process - 16:25 TOMAS TECH CO., LTD. Project progress work #740 (In Progress): [Development] Mobile android device and api development.
- 13:38 TOMAS TECH CO., LTD. Project progress work #740 (In Progress): [Development] Mobile android device and api development.
- - Mobile application to support android device.
- Link api to i-Reporter. - 13:29 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (03/10)Create i-Reporter form, problem in extracting data from the Data Output.
02 Oct 2024
- 17:06 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
-Modify the system according to user needs. - 17:04 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Schedule plan
-Prepare an Android project
tomorrow
-Receive process - 17:02 A.N.I. LOGISTICS, LTD. Project progress work #739 (Closed): [Development] CKD process system phase4
- [Coding]
1)Android handy
2)tablet modification Java
3)Backend web socket (php) - 16:57 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
KDPL1000 (25 %)
% Done 12% - 16:22 AH BRAKE (THAILAND) CO., LTD. Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet
- Wring & Assemble control Main master PLC , Packing Slave Box
- 16:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project
- - Support wiring lan cable
- Support installation server pc rack
01 Oct 2024
- 17:00 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735: PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
KDPA4000 (80 %)
% Done 8% - 16:42 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
Installation and training at Thai Stanley Electric Public Company Limited - 15:29 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #491 (Confirmation request): PICS - Version upgrade development support
- 13:24 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (01/10)Support i-Reporter NTPT, Create i-Reporter form
- 10:13 TOMAS TECH CO., LTD. Project progress work #736 (New): Installation Anti virus Norton 360
- install Anti virus Norton 360 on all PC (except PC personal(K.SO))
30 Sep 2024
- 23:42 TOMAS TECH CO., LTD. Project progress work #622: For internal meeting and other
- meeting with K.Oil about issue i-Reporter of NTPT
- 23:41 YAMATO ELECTRIC (THAILAND) CO., LTD. Project progress work #593: [Coding] Warehouse management system handyterminal Java
- develop android function Inbound rework/rework ng
- 16:55 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735 (In Progress): PICS handy terminal Document.
- Make Document HT Software.
KDPA2000 (80 %)
% Done 4%
- 16:52 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #735 (Closed): PICS handy terminal Document.
- Make Document HT Software.
- 16:30 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (30/09)Support i-Reporter NTPT(Meeting with K.So), Create i-Reporter form
- 16:24 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
-Adjust application follow Denso team.
tomorrow
-Install application and Training user. - 07:54 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #734 (Closed): PICS - Handy Terminal - Test confirmation
- Test confirmation
- 01:21 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #733 (Closed): Design and documentation
27 Sep 2024
- 16:16 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
create report:-
-Torque check sheet
-Jig inspection standard evaluation result sheet
-Maintenance Schedule ... - 15:49 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (27/09)Support i-Reporter NTPT, Create i-Reporter form
26 Sep 2024
- 17:40 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #493 (In Progress): REPO - Version upgrade development support
- 17:32 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #492 (In Progress): CYLC - Version upgrade development support
- 16:55 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (26/09)Support i-Reporter NTPT, Create i-Reporter form
- 16:44 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
create report:-
-Torque check sheet
-Jig inspection standard evaluation result sheet
-Maintenance Schedule ...
25 Sep 2024
- 17:52 TOMAS TECH CO., LTD. Sales support #732 (In Progress): [ Make concept & Summary cost ] Line operation monitoring
- 17:51 TOMAS TECH CO., LTD. Sales support #732 (In Progress): [ Make concept & Summary cost ] Line operation monitoring
- - Make concept and summary cost
- 17:30 THAI METALTECH CO., LTD. Sales support #731 (In Progress): installation&Training
- Handy Training
Outbound / Stock Management
- Outbound
- Schedule Outbound
- Work Outbound
- Prod... - 17:28 THAI METALTECH CO., LTD. Sales support #731 (In Progress): installation&Training
- Date 1 Pegasus
- Introduce to the WMS system Pegasus
- Schedule
- Inbound Schedule
- Inbound Schedule Det... - 16:32 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
create report:-
-Torque check sheet
-Jig inspection standard evaluation result sheet
tomorrow
create repor... - 16:21 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (25/09)Support i-Reporter NTPT, Create i-Reporter form
24 Sep 2024
- 16:40 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
create report:-
1.-แผนภูมิควบคุมสำหรับข้อมูลชนิดแปรผัน (XR Chart)
tomorrow
create report:-
2.Torque check ... - 14:53 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (24/09)Support i-Reporter NTPT
- 11:42 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #465 (Confirmation request): [Coding]ASI - Process Control System Phase2 -Java
- -update system and install new version of win app
-test report with customer
-config printer - 10:51 YAMATO ELECTRIC (THAILAND) CO., LTD. Project progress work #593: [Coding] Warehouse management system handyterminal Java
- api for inbound rework/rework ng
Also available in: Atom