22:39 AIKAI LOGISTICS (THAILAND) CO., LTD Project progress work #723 (Closed): [Install] Install of srims WMS of Seino information systems
https://drive.google.com/file/d/1I0VTOsLUFqXaoCEZU0dtGWy1NH-kEDQy/view?usp=sharing Ryo Nozaki
22:37 AIKAI LOGISTICS (THAILAND) CO., LTD Project progress work #723 (Closed): [Install] Install of srims WMS of Seino information systems
Ryo Nozaki
22:21 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #720: Specification and system design
- Update dashboard Nattapol Poeam
16:51 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
today
Move Inspector, MC Scan to first page
Add Input for Factory name
Cancel Line group
tomorrow
Move Inspector...
Priroj Neamjarn
16:48 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #721: Modify PC Software.
Modify PC Software. Kamol Anekchatnuntakool
14:01 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(18/09)Create i-Reporter form Panthita Roekdee
11:39 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #674 (Confirmation request): [Installation]Process Control System phase2
Soraya Norasing

17 Sep 2024

16:50 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #721: Modify PC Software.
Modify PC Software. Kamol Anekchatnuntakool
16:20 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
today
-Test rate function
-Test bar chart.
-Deploy to server
Priroj Neamjarn
14:24 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(17/09)create i-Reporter form (8 form about HR, GA, ACC section)(2/2) Panthita Roekdee

16 Sep 2024

16:58 NTN MANUFACTURING (THAILAND) CO., LTD. Sales support #681 (In Progress): Concept and summarize cost
Nattapol Poeam
16:58 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #720 (In Progress): Specification and system design
Nattapol Poeam
16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #720 (Closed): Specification and system design
- Specification design
- System design
Nattapol Poeam
16:57 TOMAS TECH CO., LTD. Sales support #722 (In Progress): MCCT Make concept and summary cost
Nattapol Poeam
16:52 TOMAS TECH CO., LTD. Sales support #722 (In Progress): MCCT Make concept and summary cost
- Make concept link data from CMM Nattapol Poeam
16:57 TOMAS TECH CO., LTD. Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI
Nattapol Poeam
16:29 TOMAS TECH CO., LTD. Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI
- Make concept
- Presentation
- Demo
Nattapol Poeam
16:51 TOMAS TECH CO., LTD. Sales support #719 (In Progress): Traceability new line for ADVICS
Nattapol Poeam
16:35 TOMAS TECH CO., LTD. Sales support #719 (In Progress): Traceability new line for ADVICS
- Make concept
- Summarize cost
Nattapol Poeam
16:47 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #721 (In Progress): Modify PC Software.
Modify PC Software. Kamol Anekchatnuntakool
16:46 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #721 (Closed): Modify PC Software.
Modify PC Software. Kamol Anekchatnuntakool
16:43 TOMAS TECH CO., LTD. Project progress work #639 (Confirmation request): [ concept and estimate cost ] CCTV installation for ANI
Nattapol Poeam
16:42 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
today
-Include rate to function for calculate in system.
tomorrow
-Test rate function
-Test bar chart.
-Deploy t...
Priroj Neamjarn
14:44 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(16/09)create i-Reporter form (8 form about HR, GA, ACC section)(1/2) Panthita Roekdee

13 Sep 2024

16:56 TOMAS TECH CO., LTD. Sales support #695 (In Progress): Concept install label print and collection signal machine
Konlawat Saechee
16:55 TOMAS TECH CO., LTD. Project progress work #677 (In Progress): Weighing scale test (MATTO)
Konlawat Saechee
16:55 TOMAS TECH CO., LTD. Sales support #710 (In Progress): Demo Keyence 4 Set
Konlawat Saechee
16:54 TOMAS TECH CO., LTD. Sales support #711 (In Progress): LAZADA Barcode reader systems
Konlawat Saechee
16:52 OTICS (THAILAND) CO., LTD. Project progress work #717 (Closed): Air Conditioner Installation
installation Teeradon Yuensakul
16:48 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662 (Confirmation request): PICS - Version upgrade development support handy terminal
Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP...
Kamol Anekchatnuntakool
16:48 ADVICS MANUFACTURING (THAILAND) CO., LTD. Problem-Bug #716 (Closed): PLC data clear error
PLC debug programing about data clear error Konlawat Saechee
16:36 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
today
-Change the function cost bar chart to an energy cost bar chart.
-Create a form for setting rates.
next time...
Priroj Neamjarn
15:28 OTICS (THAILAND) CO., LTD. Project progress work #679 (Closed): Power meter monitoring
Ryo Nozaki
15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 ,
Ryo Nozaki
15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #611 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project
Ryo Nozaki
15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #588 (Closed): Flow Meter and Power Meter MODBUS protocol setting
Ryo Nozaki
15:34 THAI NIPPON FOODS CO., LTD. Problem-Bug #613 (Closed): Fix comment machine operation and water treatment
Ryo Nozaki
15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #407 (Closed): [Installation&On-site support] Production IoT system for JATH
Ryo Nozaki
15:34 TOMAS TECH CO., LTD. Project progress work #615 (Closed): Setup notebook for working
Ryo Nozaki
15:34 TOMAS TECH CO., LTD. Project progress work #612 (Closed): demo kit safety door system
Ryo Nozaki
15:30 THAI METALTECH CO., LTD. Project progress work #621 (Closed): Meeting
Ryo Nozaki
15:29 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #616 (Closed): Software and Hardware Configuration Factory1 , 2 and 3
Ryo Nozaki
15:29 AH BRAKE (THAILAND) CO., LTD. Sales support #628 (Closed): design 3d for estimate cost
Ryo Nozaki
15:28 AIKAI LOGISTICS (THAILAND) CO., LTD Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application
Ryo Nozaki
15:28 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #635 (Closed): support Bekido Project
Ryo Nozaki
15:28 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #669 (Closed): Handy terminal stock management system.
Ryo Nozaki
15:28 AH BRAKE (THAILAND) CO., LTD. Project progress work #657 (Closed): Learning loss analyze
Ryo Nozaki
15:28 TOMAS TECH CO., LTD. Project progress work #656 (Closed): Demo Develop HT Software for Receive weight data and Send to Printer.
Ryo Nozaki
15:28 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work #687 (Closed): Network Diagram
Ryo Nozaki
15:28 DAIFUKU (THAILAND) LTD. Project progress work #701 (Closed): [Area3] Site survey
Ryo Nozaki
15:28 ACME INDUSTRY CO.,LTD. Project progress work #676 (Closed): Develop HT Software for scan TAG.
Ryo Nozaki
15:28 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #702 (Closed): Modify HT Stock Software.
Ryo Nozaki
15:28 TOMAS TECH CO., LTD. Project progress work #672 (Closed): Summarize concept re-layout machine line NMT for ATA
Ryo Nozaki
15:28 TOMAS TECH CO., LTD. Project progress work #706 (Closed): Demo Develop HT Software for Scan data and Receive weight data.
Ryo Nozaki
15:28 TOMAS TECH CO., LTD. Sales support #680 (Closed): alpha - vision inspection
Ryo Nozaki
15:12 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(13/09) Create document forms Panthita Roekdee

12 Sep 2024

17:51 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(12/09) Create document forms about HR, GA, ACC section Panthita Roekdee
17:01 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP...
Kamol Anekchatnuntakool
16:46 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
today
-Change the function cost bar chart to an energy cost bar chart.
tomorrow
-Change the function cost bar char...
Priroj Neamjarn

11 Sep 2024

16:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP...
Kamol Anekchatnuntakool
16:06 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
today
-Training end user
tomorrow
-Modify the program according to users request additions.
Priroj Neamjarn
14:26 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(11/09) Uninstall i-Reporter for Windows 5.2.24070 there is a problem with not allowing access when exiting the progr... Panthita Roekdee
13:45 A.N.I. LOGISTICS, LTD. Project progress work #131: [Coding]Android handy and tablet modification Java
Check the problems reported by customers.
-fix table case : sub leader confirm can't confirm status cancel
-fix han...
Soraya Norasing

10 Sep 2024

16:57 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP...
Kamol Anekchatnuntakool
16:04 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
today
-Add function show color after user is confirm message.
-Crate package and log file to edit table. It have fo...
Priroj Neamjarn
13:20 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(10/09) create an i-Reporter form for these two files and See other sample forms on Document Manager Panthita Roekdee
12:59 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #715 (In Progress): CAPS - Installation
Thanthima Phaengkham
10:22 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #715 (Closed): CAPS - Installation
CAPS - Installation Thanthima Phaengkham
12:58 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #491 (In Progress): PICS - Version upgrade development support
Thanthima Phaengkham
10:17 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #490 (Confirmation request): CAPS - Version upgrade development support
Thanthima Phaengkham
10:16 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #489 (Confirmation request): SALE - Operation test confirmation/Specification creation
Thanthima Phaengkham
10:04 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #488 (Confirmation request): STEP - Operation test confirmation/Specification creation
Thanthima Phaengkham
09:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #485 (Confirmation request): PICS - Operation test confirmation/Specification creation
Thanthima Phaengkham
09:42 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #487 (Confirmation request): REPO - Operation test confirmation/Specification creation
Thanthima Phaengkham
09:21 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #486 (Confirmation request): CYLC - Operation test confirmation/Specification creation
Thanthima Phaengkham
09:02 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #484 (Confirmation request): CAPS - Operation test confirmation/Specification creation
Thanthima Phaengkham

09 Sep 2024

16:46 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP...
Kamol Anekchatnuntakool
16:43 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
today
-Add function show color after user is confirm message.
tomorrow
-Crate package and log file to edit table. ...
Priroj Neamjarn
16:30 TOMAS TECH CO., LTD. Project progress work #706 (Close request): Demo Develop HT Software for Scan data and Receive weight data.
Kittisak Isarapongporn
15:24 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
(09/09) First day of work, install the program i-Reporter, meeting on MSTeams with Ms. So 11.00-12.00, try the progra... Panthita Roekdee
15:11 TOMAS TECH CO., LTD. Project progress work #714 (New): For internal meeting and other
internal meeting and other Panthita Roekdee
 