Activity
From 07 Sep 2024 to 16 Sep 2024
16 Sep 2024
- 16:58 NTN MANUFACTURING (THAILAND) CO., LTD. Sales support #681 (In Progress): Concept and summarize cost
- 16:58 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #720 (In Progress): Specification and system design
- 16:40 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #720 (Closed): Specification and system design
- - Specification design
- System design - 16:57 TOMAS TECH CO., LTD. Sales support #722 (In Progress): MCCT Make concept and summary cost
- 16:52 TOMAS TECH CO., LTD. Sales support #722 (In Progress): MCCT Make concept and summary cost
- - Make concept link data from CMM
- 16:57 TOMAS TECH CO., LTD. Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI
- 16:29 TOMAS TECH CO., LTD. Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI
- - Make concept
- Presentation
- Demo - 16:51 TOMAS TECH CO., LTD. Sales support #719 (In Progress): Traceability new line for ADVICS
- 16:35 TOMAS TECH CO., LTD. Sales support #719 (In Progress): Traceability new line for ADVICS
- - Make concept
- Summarize cost - 16:47 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #721 (In Progress): Modify PC Software.
- Modify PC Software.
- 16:46 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. Project progress work #721 (Closed): Modify PC Software.
- Modify PC Software.
- 16:43 TOMAS TECH CO., LTD. Project progress work #639 (Confirmation request): [ concept and estimate cost ] CCTV installation for ANI
- 16:42 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
- today
-Include rate to function for calculate in system.
tomorrow
-Test rate function
-Test bar chart.
-Deploy t... - 14:44 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (16/09)create i-Reporter form (8 form about HR, GA, ACC section)(1/2)
13 Sep 2024
- 16:56 TOMAS TECH CO., LTD. Sales support #695 (In Progress): Concept install label print and collection signal machine
- 16:55 TOMAS TECH CO., LTD. Project progress work #677 (In Progress): Weighing scale test (MATTO)
- 16:55 TOMAS TECH CO., LTD. Sales support #710 (In Progress): Demo Keyence 4 Set
- 16:54 TOMAS TECH CO., LTD. Sales support #711 (In Progress): LAZADA Barcode reader systems
- 16:52 OTICS (THAILAND) CO., LTD. Project progress work #717 (Closed): Air Conditioner Installation
- installation
- 16:48 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662 (Confirmation request): PICS - Version upgrade development support handy terminal
- Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP... - 16:48 ADVICS MANUFACTURING (THAILAND) CO., LTD. Problem-Bug #716 (Closed): PLC data clear error
- PLC debug programing about data clear error
- 16:36 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
- today
-Change the function cost bar chart to an energy cost bar chart.
-Create a form for setting rates.
next time... - 15:28 OTICS (THAILAND) CO., LTD. Project progress work #679 (Closed): Power meter monitoring
- 15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 ,
- 15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #611 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project
- 15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #588 (Closed): Flow Meter and Power Meter MODBUS protocol setting
- 15:34 THAI NIPPON FOODS CO., LTD. Problem-Bug #613 (Closed): Fix comment machine operation and water treatment
- 15:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #407 (Closed): [Installation&On-site support] Production IoT system for JATH
- 15:34 TOMAS TECH CO., LTD. Project progress work #615 (Closed): Setup notebook for working
- 15:34 TOMAS TECH CO., LTD. Project progress work #612 (Closed): demo kit safety door system
- 15:30 THAI METALTECH CO., LTD. Project progress work #621 (Closed): Meeting
- 15:29 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #616 (Closed): Software and Hardware Configuration Factory1 , 2 and 3
- 15:29 AH BRAKE (THAILAND) CO., LTD. Sales support #628 (Closed): design 3d for estimate cost
- 15:28 AIKAI LOGISTICS (THAILAND) CO., LTD Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application
- 15:28 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #635 (Closed): support Bekido Project
- 15:28 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #669 (Closed): Handy terminal stock management system.
- 15:28 AH BRAKE (THAILAND) CO., LTD. Project progress work #657 (Closed): Learning loss analyze
- 15:28 TOMAS TECH CO., LTD. Project progress work #656 (Closed): Demo Develop HT Software for Receive weight data and Send to Printer.
- 15:28 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work #687 (Closed): Network Diagram
- 15:28 DAIFUKU (THAILAND) LTD. Project progress work #701 (Closed): [Area3] Site survey
- 15:28 ACME INDUSTRY CO.,LTD. Project progress work #676 (Closed): Develop HT Software for scan TAG.
- 15:28 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. Project progress work #702 (Closed): Modify HT Stock Software.
- 15:28 TOMAS TECH CO., LTD. Project progress work #672 (Closed): Summarize concept re-layout machine line NMT for ATA
- 15:28 TOMAS TECH CO., LTD. Project progress work #706 (Closed): Demo Develop HT Software for Scan data and Receive weight data.
- 15:28 TOMAS TECH CO., LTD. Sales support #680 (Closed): alpha - vision inspection
- 15:12 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (13/09) Create document forms
12 Sep 2024
- 17:51 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (12/09) Create document forms about HR, GA, ACC section
- 17:01 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
- Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP... - 16:46 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
- today
-Change the function cost bar chart to an energy cost bar chart.
tomorrow
-Change the function cost bar char...
11 Sep 2024
- 16:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
- Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP... - 16:06 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
-Training end user
tomorrow
-Modify the program according to users request additions. - 14:26 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (11/09) Uninstall i-Reporter for Windows 5.2.24070 there is a problem with not allowing access when exiting the progr...
- 13:45 A.N.I. LOGISTICS, LTD. Project progress work #131: [Coding]Android handy and tablet modification Java
- Check the problems reported by customers.
-fix table case : sub leader confirm can't confirm status cancel
-fix han...
10 Sep 2024
- 16:57 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
- Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP... - 16:04 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
-Add function show color after user is confirm message.
-Crate package and log file to edit table. It have fo... - 13:20 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (10/09) create an i-Reporter form for these two files and See other sample forms on Document Manager
- 12:59 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #715 (In Progress): CAPS - Installation
- 10:22 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #715 (Closed): CAPS - Installation
- CAPS - Installation
- 12:58 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #491 (In Progress): PICS - Version upgrade development support
- 10:17 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #490 (Confirmation request): CAPS - Version upgrade development support
- 10:16 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #489 (Confirmation request): SALE - Operation test confirmation/Specification creation
- 10:04 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #488 (Confirmation request): STEP - Operation test confirmation/Specification creation
- 09:47 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #485 (Confirmation request): PICS - Operation test confirmation/Specification creation
- 09:42 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #487 (Confirmation request): REPO - Operation test confirmation/Specification creation
- 09:21 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #486 (Confirmation request): CYLC - Operation test confirmation/Specification creation
- 09:02 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #484 (Confirmation request): CAPS - Operation test confirmation/Specification creation
09 Sep 2024
- 16:46 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work #662: PICS - Version upgrade development support handy terminal
- Modify HT Software.
KDPA2000 100%
KDPA4000 100%
KDPL1000 100%
KDPP2000 100%
KDPP5000 100%
KDPP6000 100%
KDPP... - 16:43 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD Project progress work #607: [Coding] Web app Daily check project C#, HTML, CSS and JS
- today
-Add function show color after user is confirm message.
tomorrow
-Crate package and log file to edit table. ... - 16:30 TOMAS TECH CO., LTD. Project progress work #706 (Close request): Demo Develop HT Software for Scan data and Receive weight data.
- 15:24 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (09/09) First day of work, install the program i-Reporter, meeting on MSTeams with Ms. So 11.00-12.00, try the progra...
- 15:11 TOMAS TECH CO., LTD. Project progress work #714 (New): For internal meeting and other
- internal meeting and other
07 Sep 2024
- 16:31 OTICS (THAILAND) CO., LTD. Project progress work #679: Power meter monitoring
- -today
Fix function forecast and receive real-time log power