03 May 2024

16:54 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
BluetoothPrinter Anonymous

02 May 2024

21:32 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #484 (Closed): CAPS - Operation test confirmation/Specification creation)
Check old source code. Modify if any problem. Thanthima Phaengkham
20:39 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #484 (Closed): CAPS - Operation test confirmation/Specification creation)
Check old source code. Modify if any problem. Thanthima Phaengkham
13:30 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #484 (Closed): CAPS - Operation test confirmation/Specification creation)
Check old source code. Modify if any problem. Thanthima Phaengkham
13:24 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #484 (Closed): CAPS - Operation test confirmation/Specification creation)
Check old source code. Modify if any problem. Thanthima Phaengkham
13:22 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #484 (Closed): CAPS - Operation test confirmation/Specification creation)
Check old source code. Modify if any problem. Thanthima Phaengkham
12:33 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #484 (Closed): CAPS - Operation test confirmation/Specification creation)
Check old source code. Modify if any problem. Thanthima Phaengkham
17:47 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
Anonymous
17:47 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
Anonymous
17:47 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
Anonymous
09:40 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
api function Anonymous
09:40 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
Send data to api function Anonymous
09:39 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
web scheduler grouping Anonymous
09:38 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
api function Anonymous
17:47 A.N.I. LOGISTICS, LTD. 8.00 hours (Problem-Bug #526 (Closed): [Installation&On-site support] CKD process management system phase3 for ANI)
Kittisak Isarapongporn
17:46 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
17:45 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
17:45 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
17:40 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
17:39 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
17:17 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
update status to NST_COMPL_INPUT table Anonymous
09:35 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
09:35 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
09:34 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
09:34 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
09:34 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
09:33 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
09:33 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Anonymous
17:43 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #462 (Closed): HT_MAST : Duplicate outbound bug)
funtion print bluetooth Anonymous
17:43 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #462 (Closed): HT_MAST : Duplicate outbound bug)
funtion print bluetooth Anonymous
17:38 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
Anonymous
17:37 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
exp date Anonymous
17:36 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
api function Anonymous
17:33 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
Anonymous
17:33 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
Anonymous
17:33 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
Anonymous
17:32 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
Anonymous
17:30 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #516 (New): Narupot Muangsiri Taking Day off January-December 2024)
Anonymous
17:30 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #516 (New): Narupot Muangsiri Taking Day off January-December 2024)
Anonymous
17:21 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Problem-Bug #76 (Closed): NSET - Reprint FG slip & Traceability system by Handy)
Anonymous
17:21 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Problem-Bug #76 (Closed): NSET - Reprint FG slip & Traceability system by Handy)
Anonymous
17:21 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Problem-Bug #76 (Closed): NSET - Reprint FG slip & Traceability system by Handy)
Anonymous
09:29 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Problem-Bug #76 (Closed): NSET - Reprint FG slip & Traceability system by Handy)
FIX Anonymous
09:29 NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 8.00 hours (Problem-Bug #76 (Closed): NSET - Reprint FG slip & Traceability system by Handy)
FIX Anonymous
09:53 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
sick leave Soraya Norasing
09:26 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:26 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:26 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:25 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:25 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:25 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:25 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:24 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:23 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:23 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:22 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:21 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:20 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:19 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:19 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #445 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:16 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #442 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
09:10 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
Anonymous
00:19 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Fix for support join to the several groups Kittisak Isarapongporn
00:18 DENSO PHILIPPINES CORPORATION 4.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Fix for support join to the several groups Kittisak Isarapongporn
00:04 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Installation day 5 and UAT 2/2 Kittisak Isarapongporn
00:04 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Installation day 4 and UAT 1/2 Kittisak Isarapongporn
00:03 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Installation day 3 Kittisak Isarapongporn
00:03 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Installation day 2 Kittisak Isarapongporn
00:03 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Installation day 1 Kittisak Isarapongporn
00:02 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Web socket coding Kittisak Isarapongporn
00:02 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Web socket coding Kittisak Isarapongporn
00:01 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Web socket coding Kittisak Isarapongporn
00:01 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Web socket coding Kittisak Isarapongporn
00:01 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Web socket coding Kittisak Isarapongporn
00:00 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Web socket coding Kittisak Isarapongporn
00:11 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Problem-Bug #508 (Closed): Support after cutover)
Fix the web issues and data linkage problems Kittisak Isarapongporn

01 May 2024

23:59 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Fix issues in the punchlist Kittisak Isarapongporn
23:54 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Kittisak Isarapongporn
23:53 DENSO PHILIPPINES CORPORATION 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
Database and system design Kittisak Isarapongporn
23:49 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #507 (Closed): Modify the web application, handheld and database)
Installation and UAT 1/1 Kittisak Isarapongporn
23:49 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #507 (Closed): Modify the web application, handheld and database)
Test and fix the application Kittisak Isarapongporn
23:48 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #507 (Closed): Modify the web application, handheld and database)
Test and fix the application Kittisak Isarapongporn
16:58 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 400.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
Santi Srichankaew
 