Activity
From 22 Apr 2024 to 01 May 2024
01 May 2024
- 23:59 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
- Fix issues in the punchlist
- 23:54 DENSO Philippines Corporation 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- 23:53 DENSO Philippines Corporation 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Database and system design
- 23:49 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #507 (Closed): Modify the web application, handheld and database)
- Installation and UAT 1/1
- 23:49 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #507 (Closed): Modify the web application, handheld and database)
- Test and fix the application
- 23:48 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #507 (Closed): Modify the web application, handheld and database)
- Test and fix the application
- 16:58 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 400.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
Also available in: Atom