22:14 Minebea AccessSolutions Thai Ltd Project progress work #458 (In Progress): [On site support]Project Stock management system for MAS-T
On site support Soraya Norasing
22:13 Minebea AccessSolutions Thai Ltd Project progress work #458 (Closed): [On site support]Project Stock management system for MAS-T
On site support Project Stock management system for MAS-T Soraya Norasing
16:50 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
Develop Inner packing screen function C#.
% Done 89 %
Kamol Anekchatnuntakool
16:39 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design Data] Production Control Board
- [Design Data] Production Control Board 5W Line
Jidapha Mangkhachot

28 Feb 2024

20:30 Tomas Tech Co.,Ltd. Project progress work #457 (Confirmation request): NSET Stocktaking - check bug location not found.
- Tested the program and found no bugs.
- Contact customers and remotely view the program in action.
- Completed co...
Soraya Norasing
17:04 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design]Production Control Board
- [Design Data] Production Control Board
- [Design]Production Control Budomari I...
Jidapha Mangkhachot
16:54 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
Develop Inner packing screen function C#.
% Done 86 %
Kamol Anekchatnuntakool

27 Feb 2024

22:09 Tomas Tech Co.,Ltd. Project progress work #457 (In Progress): NSET Stocktaking - check bug location not found.
Soraya Norasing
22:09 Tomas Tech Co.,Ltd. Project progress work #457 (Closed): NSET Stocktaking - check bug location not found.
after confirmed first job. when scan location not found Soraya Norasing
22:05 Tomas Tech Co.,Ltd. Project progress work #455 (Confirmation request): Meeting about display on TV with customer
Meeting about display on TV with customer Soraya Norasing
22:04 Tomas Tech Co.,Ltd. Project progress work #456 (Confirmation request): Safety training of ASI at online
Safety training of ASI at online Soraya Norasing
18:00 Asian Stanley. International Limited Project progress work #450: Development web display
- Asian Stanley Training (9.00-11.00)
- Meeting about display on TV (14.00-17.00)
Jidapha Mangkhachot
17:57 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design Data] Production Control Budomari Information Board Jidapha Mangkhachot
16:59 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
Develop Inner packing screen function C#.
% Done 83 %
Kamol Anekchatnuntakool
09:00 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #440: Order Sheet System PC.
Test and Modify Order Sheet System PC [Onstie]. Kamol Anekchatnuntakool

26 Feb 2024

10:51 Tomas Tech Co.,Ltd. Project progress work #456 (Closed): Safety training of ASI at online
Safety training Soraya Norasing
10:49 Tomas Tech Co.,Ltd. Project progress work #455 (Closed): Meeting about display on TV with customer
Summary of specs display on TV project Soraya Norasing
10:22 Tomas Tech Co.,Ltd. Project progress work #454 (Confirmation request): Internal meeting with new member (K.Jidapha)
-Explain how to use the calendar.
-Explain how to use the redmine.
-Explain the database of ASI for display on TV
Soraya Norasing
10:21 Tomas Tech Co.,Ltd. Project progress work #454 (Closed): Internal meeting with new member (K.Jidapha)
-Explain how to use the calendar.
-Explain how to use the redmine.
-Explain the database of ASI for display on TV
Soraya Norasing

23 Feb 2024

19:18 YAMADA SOMBOON CO., LTD Sales support #453 (In Progress): Machine operation by IoT
Nattapol Poeam
19:18 YAMADA SOMBOON CO., LTD Sales support #453 (Closed): Machine operation by IoT
[19/02/24]
- Site survey with TOMAS EN Team.
- Check communication of wifi in machine
- Wifi communication protoco...
Nattapol Poeam
16:48 A.N.I. LOGISTICS, LTD. Project progress work #452 (In Progress): POST-SALES support
Kittisak Isarapongporn
16:48 A.N.I. LOGISTICS, LTD. Project progress work #452 (Closed): POST-SALES support
For support issues after system launch Kittisak Isarapongporn
16:42 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design] Production Control Budomari Information Board
- [Design Data] Production Control Budomari Information B...
Jidapha Mangkhachot
07:57 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #440: Order Sheet System PC.
Install Order Sheet System PC [Onstie]. Kamol Anekchatnuntakool

22 Feb 2024

16:35 Thai Nippon foods Co.,Ltd. Project progress work #451 (In Progress): Water treatment.
Suchin Viyasing
16:33 Thai Nippon foods Co.,Ltd. Project progress work #451 (Closed): Water treatment.
Check equipment price compare from supplier ..
Design drawing
Suchin Viyasing
08:40 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design]Production Control Board
- [Design Data] Production Control Board
Jidapha Mangkhachot
08:35 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design] Production Control Board 5W Line
- [Design] Production Control Board
Jidapha Mangkhachot
08:34 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design] Production Control Board 5W Line Jidapha Mangkhachot
08:33 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design] Production Control Budomari Information Board Jidapha Mangkhachot
08:31 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design] Production Control Budomari Information Board Jidapha Mangkhachot
08:31 Asian Stanley. International Limited Project progress work #450: Development web display
-[Design] Production Control Budomari Information Board Jidapha Mangkhachot
08:29 Asian Stanley. International Limited Project progress work #450: Development web display
- [Design] Production Control Board
- [Design Data] Production Control Board
Jidapha Mangkhachot
08:28 Asian Stanley. International Limited Project progress work #450 (In Progress): Development web display
- [Design]Production Control Board
- [Design Data] Production Control Board
Jidapha Mangkhachot
08:26 Asian Stanley. International Limited Project progress work #450 (Closed): Development web display
- Production Control Budomari Information Board
- Production Control Board 5W Line
- Production Control Board
Jidapha Mangkhachot

21 Feb 2024

19:22 Thai Honda Manufacturing Co., Ltd Sales support #237 (Closed): Make proposal for IoT system
Ryo Nozaki
19:21 Matsumoto Kosan (Thailand) Co.,Ltd. Sales support #271 (Closed): ConMas i-Reporter proposal for Matsumoto Kosan (Thailand) Co.,Ltd.
Ryo Nozaki
19:20 ATA Casting Technology Co., Ltd. Sales support #71 (Closed): Machine operation monitoring
Ryo Nozaki
19:20 Asian Stanley. International Limited Project progress work #376 (Closed): Disscuss about new screen concept with ASI menber
Ryo Nozaki
19:18 Tomas Tech Co.,Ltd. Sales support #387 (Closed): Samurai asia film movie and interview
Ryo Nozaki
19:18 Tomas Tech Co.,Ltd. Sales support #386 (Closed): Webseminar 2024/2/15
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #411 (Closed): [ Task ] Drawing design for Master control box
Ryo Nozaki
19:14 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #401 (Closed): Site survey for confrim location display
Ryo Nozaki
19:14 Tomas Tech Co.,Ltd. Project progress work #398 (Closed): Make concept and summarize equipment for Interlock system prohect
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #397 (Closed): Wiring cable in the cabinet
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #396 (Closed): Meeting From JATH about IoT of infrastructure
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #355 (Closed): Deverlop OEE % data analysis
Ryo Nozaki
19:14 Tomas Tech Co.,Ltd. Project progress work #354 (Closed): Lernning PLC Keyence KV-8000
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #328 (Closed): Crate IoT data collection box for JATH
Ryo Nozaki
19:14 Tomas Tech Co.,Ltd. Sales support #312 (Closed): Fanuc traning and appointment Fanuc staff
Ryo Nozaki
19:14 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod
Ryo Nozaki
19:14 ATA Casting Technology Co., Ltd. Problem-Bug #215 (Closed): Request verification of the data collection of machine
Ryo Nozaki
19:14 BIG Star Co.,Ltd Sales support #209 (Closed): Shoe size sorting machine project Concept proposal
Ryo Nozaki
19:14 Thai Nippon foods Co.,Ltd. Project progress work #201 (Closed): Summary of all equipment for use in the Machine operation monitoring systems project.
Ryo Nozaki
19:14 Thai Nippon foods Co.,Ltd. Sales support #175 (Closed): EV charger installation project
Ryo Nozaki
19:14 Asteer (Thailand) Co., Ltd. Project progress work #109 (Closed): [On-site support]Support after cutover
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard
Ryo Nozaki
19:14 Thai Nippon foods Co.,Ltd. Project progress work #422 (Closed): Install PLC programs
Ryo Nozaki
19:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #446 (Closed): [ Task ] Drawing design for Master control box
Ryo Nozaki
19:14 Thai Nippon foods Co.,Ltd. Project progress work #438 (Closed): Survery Essilor manufacturing
Ryo Nozaki
19:14 Thai Nippon foods Co.,Ltd. Project progress work #437 (Closed): support ANI
Ryo Nozaki
19:14 Matsumoto Kosan (Thailand) Co.,Ltd. Sales support #435 (Closed): Meeting and site survey about collect data from Machine CNC
Ryo Nozaki
19:14 Tomas Tech Co.,Ltd. Project progress work #433 (Closed): ASI online training safety
Ryo Nozaki
19:05 Tomas Tech Co.,Ltd. Sales support #449 (New): Sales for new and follow up each customer
The man-hours related to sales activities are summarized for Feblary here. Ryo Nozaki
19:04 Tomas Tech Co.,Ltd. Sales support #439 (In Progress): Thai Shinmaywa meeting and proposal to New stock management system
Ryo Nozaki
16:55 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #141: [Task]Deverlop HMI Bekido and OA monitoring
Update datalink PLC KV-8000
Setting configulation router RUT240 share IP Adress
Setting configulation Access point...
Santi Srichankaew
16:49 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #440: Order Sheet System PC.
Develop Order Sheet System PC. Kamol Anekchatnuntakool
16:43 A.N.I. LOGISTICS, LTD. Project progress work #131 (In Progress): [Coding]Android handy and tablet modification Java
Kittisak Isarapongporn
16:41 A.N.I. LOGISTICS, LTD. Project progress work #134 (In Progress): [Installation&On-site support] CKD process management system phase3 for ANI
Kittisak Isarapongporn
16:39 A.N.I. LOGISTICS, LTD. Project progress work #129 (In Progress): [Coding]PHP Pegasus web function
Kittisak Isarapongporn
16:34 Minebea AccessSolutions Thai Ltd Project progress work #103 (In Progress): [Installation&On-site support]Project Stock management system for MAS-T
Kittisak Isarapongporn

20 Feb 2024

16:53 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #440: Order Sheet System PC.
Develop Order Sheet System PC. Kamol Anekchatnuntakool
15:46 Minebea AccessSolutions Thai Ltd Project progress work #447 (Closed): create manual document for MAST
-Pegasus System Stock management Manual Document
-Handy Terminal Stock management Manual Document
Soraya Norasing
15:26 Minebea AccessSolutions Thai Ltd Project progress work #97: [Coding]Android handyterminal BTA500
last version update(20/02/2024) Soraya Norasing
08:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #446 (Close request): [ Task ] Drawing design for Master control box
Kittisak Isarapongporn
08:50 Thai Nippon foods Co.,Ltd. Project progress work #438 (Close request): Survery Essilor manufacturing
Kittisak Isarapongporn
08:50 Thai Nippon foods Co.,Ltd. Project progress work #437 (Close request): support ANI
Kittisak Isarapongporn
08:50 Matsumoto Kosan (Thailand) Co.,Ltd. Sales support #435 (Close request): Meeting and site survey about collect data from Machine CNC
Kittisak Isarapongporn
08:50 Tomas Tech Co.,Ltd. Project progress work #433 (Close request): ASI online training safety
Kittisak Isarapongporn
08:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #411 (Close request): [ Task ] Drawing design for Master control box
Kittisak Isarapongporn
08:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #397 (Close request): Wiring cable in the cabinet
Kittisak Isarapongporn
 