Activity
From 28 Jan 2024 to 06 Feb 2024
06 Feb 2024
- 16:41 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #396 (Closed): Meeting From JATH about IoT of infrastructure)
- Meeting IOT Infrastructure
- 16:39 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #410 (Closed): [ Task ] Program and Dashboard Development )
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION
- 16:37 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #428 (Closed): Servey plant installation power meter to panel control)
- Meeting From JATH about IoT of infrastructure
- 16:33 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Function PLC Data link
- 16:29 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Power on TB-Box Plant A and Data monitor from Machine Spiral
- 16:27 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Monitoring and communication test on Plant A
- 15:57 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #422 (Closed): Install PLC programs )
- Install programs for PLC and HMI
- 15:55 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Test PLC signal reception
- 09:18 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Install Inbound Outbound Management System for MAST.
05 Feb 2024
- 10:12 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod)
- install Traceability system Line MC25&MC26.
04 Feb 2024
- 23:41 ATA Casting Technology Co., Ltd. 4.00 hours (Project progress work #91 (Closed): Modify Pegasus.)
- Edited the data preference report and layout. Remote install and test the scripts.
- 23:39 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
- Label integration to web API and test the outbound handy function
- 23:37 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
- Set up and test the printers and develop the label layout
- 23:36 Minebea AccessSolutions Thai Ltd 3.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
- Store procedure for ExportInventory
- 20:29 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #420 (Closed): Go to a meeting at topre)
- Went to a meeting at topre (thailand) co., ltd.
- 20:25 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #419 (Closed): Sick leave to go to hospital)
- Take sick leave to see a doctor
- 20:24 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #421 (Closed): Prepare a demo kit for a meeting at TOPRE.)
- Test the demo set to go to a meeting at topre (thailand) co., ltd.
- 20:23 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #418 (Closed): Went to a work meeting in Rayong.)
- Go to a meeting
- 20:20 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Run the cable from the ceiling down to the plantB machine.
- 20:18 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Finished wiring from the ceiling down to all plantB machines and installing plc connection equipment.
03 Feb 2024
- 15:31 Ebisu Foods Co Ltd. 8.00 hours (Project progress work #383 (Closed): Develop modify the master management module )
- develop the application and customize by comment's issue
- 08:55 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set all required bits in plant A
- 08:43 Thai Nippon foods Co.,Ltd. 4.00 hours (Project progress work #417 (Closed): Go solve problems on site at TNF.)
- Solve the problem of machines not working at TNF
- 08:41 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #416 (Closed): Training FANUC)
- Training FANUC
02 Feb 2024
- 23:55 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
- 23:53 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
- 1.block button 2.set Key P 3.search item 4.Meeting about programming logic with P'pum
- 19:47 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:32 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:32 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:30 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 09:30 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #426 (Closed): Configuration Between PLC And HMI&Dashboard)
- Configuration Between PLC And HMI&Dashboard Pump2&PNV
- 17:00 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod)
- develop Traceability system Line MC25&MC26.
- 16:58 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Function XD02 design for support operation monitor
- 16:56 Keyence (Thailand) Co., Ltd. 4.00 hours (Project progress work #427 (Closed): [ Support and install program ] for demo-kit WD)
- Install program and configuration equipment
- 14:34 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 14:34 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 14:34 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 09:36 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Follow team IT Jtekt
- 09:33 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #225 (Closed): CCTV Installation)
- Simple installation PC Set and Mark postion label printer
- 09:32 Thai Nippon foods Co.,Ltd. 4.00 hours (Sales support #86 (Closed): IoT Equipment for Water treatment project)
- Summarize equipment and check spec device
- 09:09 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #410 (Closed): [ Task ] Program and Dashboard Development )
- Program and Dashboard Development
01 Feb 2024
- 20:51 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #425 (Closed): Meeting with Japanese person)
- 20:50 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 4.00 hours (Sales support #239 (Closed): Handy terminal system re-placement for keyence handy terminal)
- Meeting with Kadotani and will make quote submit by 9th
- 20:43 Tomas Tech Co.,Ltd. 8.00 hours (Sales support #424 (Closed): YAMATO ELECTRIC (THAILAND) CO.,LTD create proposal and qt)
- Create document and qt
- 20:40 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. 4.00 hours (Project progress work #263 (Closed): [Requirement definition] Handy terminal stock management system for Pegasus)
- Meeting with Osada and Iyoda
- 20:39 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #423 (In Progress): HDK meeting and site survey about traceability system)
- Meeting with MD
- 20:38 Tomas Tech Co.,Ltd. 2.00 hours (Sales support #386 (Closed): Webseminar 2024/2/15)
- Samurai meeting at web
- 20:37 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 2.00 hours (Project progress work #395 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive)
- Add contact and discuss invoice information
- 19:12 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- design machine Polystar
- 08:10 Thai Nippon foods Co.,Ltd. 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Design main program
- 18:19 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- 17:39 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
- Create the sp_insert_export_inventory for preparing inventory data. Edit ExportOutbound due to copy mechanic_order ->...
- 17:32 Minebea AccessSolutions Thai Ltd 1.00 hour (Project progress work #100 (Closed): [System Testing]Handyterminal and Web)
- Final check the handy function for OUTBOUND / PHOTO MATCHING
- 17:21 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod)
- develop Traceability system Line MC25&MC26.
- 09:24 Minebea AccessSolutions Thai Ltd 2.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
- fix list of p'nack
- 08:49 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #422 (Closed): Install PLC programs )
- Install PLC programs kv studio,vt studio,GX-Work2,gt designer 3
- 08:45 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Go to support at TNF
- 08:35 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #421 (Closed): Prepare a demo kit for a meeting at TOPRE.)
- Prepare a demo kit for a meeting at TOPRE.
- 08:33 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #420 (Closed): Go to a meeting at topre)
- Go to a meeting at topre
- 08:30 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #419 (Closed): Sick leave to go to hospital)
- Sick leave to go to hospital
- 08:27 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #418 (Closed): Went to a work meeting in Rayong.)
- Went to a work meeting in Rayong.
- 08:24 Thai Nippon foods Co.,Ltd. 4.00 hours (Project progress work #417 (Closed): Go solve problems on site at TNF.)
- Go solve problems on site at TNF.
- 08:20 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #416 (Closed): Training FANUC)
- Training FANUC
- 08:07 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #354 (Closed): Lernning PLC Keyence KV-8000 )
- Lernning PLC Keyence KV-8000
- 08:04 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
31 Jan 2024
- 23:55 ATA Casting Technology Co., Ltd. 8.00 hours (Project progress work #91 (Closed): Modify Pegasus.)
- Edited the data reference pages and store procedures.
- 20:07 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #405 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive)
- Drawing concept design
- 19:36 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Installation AMX PLC to Polystar machine
- 19:34 DAIFUKU (THAILAND) LTD. 8.00 hours (Sales support #415 (Closed): [Requirement and support] Installation camera Area 1-3)
- Pick up equipment of Area 3 at Daifuku and meeting at Trope
- 19:24 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- design dashboard Spiral machine
- 19:23 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit of the Spiral machine.
- 19:23 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit of the Spiral machine.
- 19:19 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- summax machine design
- 19:18 Thai Nippon foods Co.,Ltd. 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the bit that must be used by the summax machine.
- 19:16 Thai Nippon foods Co.,Ltd. 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Hi-cook machine design completed
- 19:15 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Hicook machine design
- 19:14 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- H-icook machine design
- 19:11 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit for each machine.
- 19:11 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit for each machine.
- 19:10 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Start designing the main
- 19:08 Thai Nippon foods Co.,Ltd. 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Start designing the main
- 19:01 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Organize the dashboard concept
- 19:20 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Route the I/O cables on the ceiling to the machine location.
- 19:13 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Wiring the ceiling from the plantB cabinet
- 19:06 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- config machinery and ceiling drilling Plant A
- 19:05 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- config machinery and ceiling drilling Plant A
- 18:04 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- 11:13 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- Photo matcthing
- 11:13 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- Outbound
- 11:12 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- Outbound
- 11:12 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- Qc Check
- 11:12 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- Qc Check
- 11:11 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- Qc Check
- 11:11 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound)
- 17:05 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod)
- develop Traceability system Line MC25&MC26.
- 17:02 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
- fix list of p'nack
- 16:56 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
- 16:44 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #99 (Closed): [System Testing]Handyterminal and Web)
- Final test the labeling and outbound handy functions
- 16:41 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
- Improve the BOM, Stock maintenance report and stock inquiry report
- 16:09 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet 4/8 , Leave of absence 4/8
- 16:08 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #397 (Closed): Wiring cable in the cabinet)
- Leave of absence
- 15:37 Asian Stanley. International Limited 8.00 hours (Project progress work #414 (Closed): Develop new screen of dashboard )
- develop dashboard
- 13:10 Ebisu Foods Co Ltd. 4.00 hours (Project progress work #16 (Closed): WMS Web Development )
- fixed bug and internal testing
- 13:09 Ebisu Foods Co Ltd. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- fixed bug and internal testing
- 13:08 Ebisu Foods Co Ltd. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- Training and fixed bug at Ebisu site
- 13:05 Ebisu Foods Co Ltd. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- develop the application and customize by comment's issue
- 11:10 Nidec Techno Motor (Thailand) Co.,Ltd. 8.00 hours (Problem-Bug #382 (Closed): Label format vietnam)
30 Jan 2024
- 23:55 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 23:55 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 23:54 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 23:54 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 23:54 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 23:54 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 23:53 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
- Support to start using WMS the system for handy terminal & pegasus system
- 23:51 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 4.00 hours (Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod)
- Discuss about Knuckle Line MC25&MC26 Traceability system
- 17:01 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod)
- develop Traceability system Line MC25&MC26.
- 23:49 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Install OS on Server and config DB on Server
- 21:35 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #328 (Closed): Crate IoT data collection box for JATH)
- Send demo box to Mantenance JATH team
- 21:29 DAIFUKU (THAILAND) LTD. 4.00 hours (Project progress work #406 (Closed): Prepare equipment for installation for Area1)
- Pick up equipment of Area 3 at Daifuku
- 21:27 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #405 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive)
- Meeting and site survey
- 21:18 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #225 (Closed): CCTV Installation)
- Support on-site about confrim power cable and lan cable in table
- 21:16 Tomas Tech Co.,Ltd. 8.00 hours (Sales support #404 (In Progress): OTICS (Thailand) Company Limited meeting about IoT system and site servey)
- Site survey MDB,Panel control point
- 21:08 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #403 (Closed): Summarize equipment of Water treatment project)
- Summarize equipment
- 21:03 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #402 (Closed): Modification program for record S/N to CF-Card)
- On-site service tuning camera SRX-300
- 21:02 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #402 (Closed): Modification program for record S/N to CF-Card)
- Support after install program to machine
- 21:01 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #402 (Closed): Modification program for record S/N to CF-Card)
- Install program line MC30 OP80
- 21:01 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #402 (Closed): Modification program for record S/N to CF-Card)
- Install program line MC30 OP80
- 20:55 Thai Nippon foods Co.,Ltd. 4.00 hours (Sales support #86 (Closed): IoT Equipment for Water treatment project)
- Site survey
- 20:52 Tomas Tech Co.,Ltd. 5.00 hours (Sales support #269 (Closed): Automation for receiving and shipping of Fabrinet )
- Meeting about overall concept at site
- 20:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Database and function design
- 20:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Database and function design
- 20:42 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Database and function design
- 20:42 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Database and function design
- 20:42 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Database and function design
- 20:45 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #312 (Closed): Fanuc traning and appointment Fanuc staff)
- Trining function of Fanuc MT-Link
- 20:44 Thai Nippon foods Co.,Ltd. 4.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- On-site to support problem machine brakedown
- 20:36 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- On-site support after installation module PLC of Polystar
- 20:27 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Installation TB-Box in Plant A
- 20:39 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #401 (Closed): Site survey for confrim location display)
- Site survey
- 20:26 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #243 (Closed): [ Task ] Program design and development )
- Program design
- 20:25 A.N.I. LOGISTICS, LTD. 3.00 hours (Project progress work #128 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Explain the system and new requirements of web to K.Duang
- 20:20 BIG Star Co.,Ltd 8.00 hours (Sales support #209 (Closed): Shoe size sorting machine project Concept proposal )
- Internal meeting with Keyence team
- 20:08 BIG Star Co.,Ltd 8.00 hours (Sales support #209 (Closed): Shoe size sorting machine project Concept proposal )
- Summarize machine concept and discus other function machine
- 20:07 BIG Star Co.,Ltd 8.00 hours (Sales support #209 (Closed): Shoe size sorting machine project Concept proposal )
- Meeting about presentation overall concept and function machine *Customer request to change concept of machine
- 20:19 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #398 (Closed): Make concept and summarize equipment for Interlock system prohect)
- Make and summarize concept of insterlock system
- 17:08 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
- 17:02 Minebea AccessSolutions Thai Ltd 5.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
- Create the layout for labels
- 17:04 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #101 (Closed): [System Testing]Handyterminal and Web)
- Outbound and web function test
- 16:54 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 0.00 hour (Project progress work #397 (Closed): Wiring cable in the cabinet)
- Leave of absence
- 16:53 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #397 (Closed): Wiring cable in the cabinet)
- 16:51 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet
- 16:49 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet
- 16:48 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet
- 08:24 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:24 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:23 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop dashboard bekido all function any line operation 80%
- 08:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:15 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:15 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:15 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:15 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION 30%
- 08:13 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #396 (Closed): Meeting From JATH about IoT of infrastructure)
- Meeting From JATH about IoT of infrastructure
29 Jan 2024
- 21:10 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #395 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive)
- Kick off meeting
- 21:07 NTPT Company Limited. 4.00 hours (Sales support #369 (Closed): NTPT prodcution planing system for NTPT)
- Meeting
- 21:07 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #394 (Closed): OTICS (Thailand) Company Limited meeting about IoT system and site servey)
- Survey
- 21:04 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #393 (Closed): Meeting with ACME INDUSTRY CO.,LTD and site survey and teaching for customer)
- Meeting
- 21:01 DENSO Philippines Corporation 4.00 hours (Project progress work #22 (Closed): Make specification document for project)
- Meeting with TIE team and KDDI
- 21:00 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #392 (Closed): Meeting at 25th Jan)
- Meeting
- 20:56 Tomas Tech Co.,Ltd. 8.00 hours (Sales support #391 (Closed): Meeting at 24th Jan)
- Meeting with customer
- 20:52 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #390 (Closed): Meeting with Wing arc and Nakamura Kikho)
- Meeting at online
- 20:48 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #389 (In Progress): THAI MATTO NS CO., LTD. proposal for Pegasus)
- Meeting
- 20:40 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #387 (Closed): Samurai asia film movie and interview )
- Film movie and interview
- 20:34 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #387 (Closed): Samurai asia film movie and interview )
- Meeting with Samurai asia
- 20:33 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #387 (Closed): Samurai asia film movie and interview )
- Create document about film company profile
- 20:37 Sekiden (Thailand)Co.,Ltd. 4.00 hours (Sales support #388 (Closed): Proposal meeting at Sekiden)
- Meeting with Kuroda and Tomitaka
- 20:31 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #386 (Closed): Webseminar 2024/2/15)
- meeting with takeda and create document
- 20:30 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #386 (Closed): Webseminar 2024/2/15)
- Meeting with kamimura and oide
- 20:29 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #374 (Closed): Meeting with CCI Automotive and proposal IoT system for Tank)
- Make quote and proposal
- 17:19 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. 8.00 hours (Project progress work #309 (Closed): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod)
- develop Traceability system Line MC25&MC26.
- 16:49 NTPT Company Limited. 4.00 hours (Project progress work #385 (Closed): NTPT Asprova introduce and demo meeting)
Also available in: Atom