- 20:07 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #405: [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- - Expain concept to SND Team
- Expain concept master control design to K.Suchin
- Reserch data about Powermeter and CT - 19:35 DAIFUKU (THAILAND) LTD. Sales support #415 (In Progress): [Requirement and support] Installation camera Area 1-3
- 19:33 DAIFUKU (THAILAND) LTD. Sales support #415 (Closed): [Requirement and support] Installation camera Area 1-3
- Installation camera area 1-3
- 18:04 Minebea AccessSolutions Thai Ltd Project progress work #381: [Coding]Android handyterminal BTA500 Outbound
- Outbound work
- print
- 17:05 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #309: [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod
- develop Traceability system Line MC25&MC26.
- 16:56 Minebea AccessSolutions Thai Ltd Project progress work #97: [Coding]Android handyterminal BTA500
- test and fix label function, inbound function
- 15:36 Asian Stanley. International Limited Project progress work #414 (Closed): Develop new screen of dashboard
- create new 3 screen.
- Production control BUDOMARI information board, this screen displays dynamic topic with user... - 10:38 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project
- - Installation program
- Connect device powermeter,Air flow sensor,Chiller system - 10:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project
- - Installation powermeter
- Installation Air flow sensor
- Installation and connect to chiller system - 10:26 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #411 (Closed): [ Task ] Drawing design for Master control box
- - Master control box design
- 10:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #410 (Closed): [ Task ] Program and Dashboard Development
- [ Task ]
- Program design
- Dashboard design
- Data report design
- Other function design - 10:10 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #409 (Closed): [Installation&On-site support] Production IoT system for JATH
- Installation IoT system for final line
- 10:03 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH
- Installation IoT for Final line Project
- 10:01 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #407 (Closed): [Installation&On-site support] Production IoT system for JATH
- Installation IoT System
- 08:06 Thai Nippon foods Co.,Ltd. Project progress work #403 (In Progress): Summarize equipment of Water treatment project
30 Jan 2024
- 21:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #405 (In Progress): [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- 21:27 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #405 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- Infrastructure IoT Project
- Kick off meeting
- Site servey
Next action
- Make drawing diagram of Control box mas... - 21:30 DAIFUKU (THAILAND) LTD. Project progress work #406 (In Progress): Prepare equipment for installation for Area1
- 21:29 DAIFUKU (THAILAND) LTD. Project progress work #406 (Closed): Prepare equipment for installation for Area1
- Prepare equipment for installation Area 1-3
- 21:17 Tomas Tech Co.,Ltd. Sales support #404 (In Progress): OTICS (Thailand) Company Limited meeting about IoT system and site servey
- 21:15 Tomas Tech Co.,Ltd. Sales support #404 (In Progress): OTICS (Thailand) Company Limited meeting about IoT system and site servey
- Site survey
- MDB and panel control point
Next acction
- Make concept and summarize equipment - 21:11 Tomas Tech Co.,Ltd. Sales support #33 (Closed): [FY2023]Common management for Anek
- 21:11 Tomas Tech Co.,Ltd. Sales support #32 (Closed): [FY2023]Common management for Yutthapong
- 21:11 Tomas Tech Co.,Ltd. Sales support #31 (Closed): [FY2023]Common management for Santi
- 21:11 Tomas Tech Co.,Ltd. Sales support #30 (Closed): [FY2023]Common management for Nattapol
- 21:11 Tomas Tech Co.,Ltd. Sales support #29 (Closed): [FY2023]Common management for Narupot
- 21:11 Tomas Tech Co.,Ltd. Sales support #28 (Closed): [FY2023]Common management for Kittisak
- 21:11 Tomas Tech Co.,Ltd. Sales support #27 (Closed): [FY2023]Common management for Kamol
- 21:11 Tomas Tech Co.,Ltd. Sales support #26 (Closed): [FY2023]Common management for Atchai
- 21:11 Tomas Tech Co.,Ltd. Sales support #25 (Closed): [FY2023]Common management for Arunwit
- 21:11 Tomas Tech Co.,Ltd. Sales support #20 (Closed): [FY2023]Common management for Soraya
- 21:10 Tomas Tech Co.,Ltd. Project progress work #398 (Confirmation request): Make concept and summarize equipment for Interlock system prohect
- 20:18 Tomas Tech Co.,Ltd. Project progress work #398 (Closed): Make concept and summarize equipment for Interlock system prohect
- - Make and summarize concept.
- Summarize equipment. - 21:07 Thai Nippon foods Co.,Ltd. Project progress work #403 (Closed): Summarize equipment of Water treatment project
- summarize equipment
- 21:04 Thai Nippon foods Co.,Ltd. Sales support #86 (In Progress): IoT Equipment for Water treatment project
- 21:00 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #402 (Closed): Modification program for record S/N to CF-Card
- [ Task ]
- Add program for record data to cf-card
- Config camera SRX-300 - 20:55 NTPT Company Limited. Project progress work #385 (Closed): NTPT Asprova introduce and demo meeting
- 20:55 Ebisu Foods Co Ltd. Project progress work #383 (Closed): Develop modify the master management module
- 20:55 A.N.I. LOGISTICS, LTD. Problem-Bug #371 (Closed): Inquiry the data about the date time of OUTER scan
- 20:55 Thai Nippon foods Co.,Ltd. Project progress work #360 (Closed): Leave of absence.
- 20:55 Thai Nippon foods Co.,Ltd. Project progress work #359 (Closed): sick leave
- 20:55 Thai Nippon foods Co.,Ltd. Project progress work #357 (Closed): sick leave.
- 20:55 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #349 (Closed): Test WiFi data transmission between PLC to PLC
- 20:55 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #345 (Closed): Design ,Install & Wiring in control box
- 16:46 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #345 (Close request): Design ,Install & Wiring in control box
- 16:45 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #345 (Confirmation request): Design ,Install & Wiring in control box
- 20:55 Tomas Tech Co.,Ltd. Sales support #315 (Closed): Shimizu correct 2 machines data from Takamatsu Mazak and sumaraize concept 27th
- 20:55 Tomas Tech Co.,Ltd. Project progress work #308 (Closed): Review and learn the source code of the project.
- 20:55 ACME INDUSTRY CO.,LTD. Project progress work #266 (Closed): Make manual document for Pegasus
- 20:55 A.N.I. LOGISTICS, LTD. Problem-Bug #214 (Closed): Found the problem with the handy being able to scan the other label [STAGING AREA]
- 20:55 Minebea AccessSolutions Thai Ltd Project progress work #96 (Closed): [Internal Design] DB and various functions, man-hour calculation
- 20:55 ACME INDUSTRY CO.,LTD. Project progress work #52 (Closed): Issue topics
- 20:55 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #356 (In Progress): Checking Process.
- Must be use PJ240003
- 20:54 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #355 (In Progress): Deverlop OEE % data analysis
- Must be use PJ230055
- 20:53 Tomas Tech Co.,Ltd. Project progress work #377 (In Progress): Demo Dashboard CKD Pressure monitor
- Must be using internal project
- 20:53 Ebisu Foods Co Ltd. Project progress work #384 (In Progress): meeting on site
- Must be using PJ230025
- 20:52 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #396 (In Progress): Meeting From JATH about IoT of infrastructure
- 20:52 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #396: Meeting From JATH about IoT of infrastructure
- Must be using PJ240004
- 16:46 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #396 (Close request): Meeting From JATH about IoT of infrastructure
- 08:13 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #396 (Confirmation request): Meeting From JATH about IoT of infrastructure
- Meeting IoT of infrastructure
- 08:12 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #396 (Closed): Meeting From JATH about IoT of infrastructure
- Meeting From JATH about IoT of infrastructure
Servey plant installation powermeter.
Confirmation scope of work.
- 20:52 Tomas Tech Co.,Ltd. Sales support #269: Automation for receiving and shipping of Fabrinet
- Concept design
1. Received
2. Shipping - 20:48 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #328 (Confirmation request): Crate IoT data collection box for JATH
- 20:45 Tomas Tech Co.,Ltd. Sales support #312 (Confirmation request): Fanuc traning and appointment Fanuc staff
- 20:39 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #401 (Confirmation request): Site survey for confrim location display
- 20:38 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #401 (Closed): Site survey for confrim location display
- Confrim scope work and location display
- 20:34 Thai Nippon foods Co.,Ltd. Project progress work #400 (Closed): Program developer and Dashboard design
- Program developer and Dashboard design
- 20:30 Thai Nippon foods Co.,Ltd. Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF
- Installation IoT sytem for Machine operation monitoring system project
- 20:26 Thai Nippon foods Co.,Ltd. Sales support #175 (Confirmation request): EV charger installation project
- 20:24 Thai Nippon foods Co.,Ltd. Project progress work #201 (Confirmation request): Summary of all equipment for use in the Machine operation monitoring systems project.
- 20:23 BIG Star Co.,Ltd Sales support #209 (Confirmation request): Shoe size sorting machine project Concept proposal
- 20:03 ATA Casting Technology Co., Ltd. Problem-Bug #215 (Confirmation request): Request verification of the data collection of machine
- 17:01 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #309: [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod
- develop Traceability system Line MC25&MC26.
- 16:53 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #397 (In Progress): Wiring cable in the cabinet
- 16:52 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #397 (Closed): Wiring cable in the cabinet
- Wiring cable in the cabinet
- 16:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #370 (Confirmation request): Install equipment & wiring in the control box 14 set.
- 08:23 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #141: [Task]Deverlop HMI Bekido and OA monitoring
- Deverlop dashboard bekido all function any line operation 80%
1.web dasboard XD-02 data ling display creat module G...
29 Jan 2024
- 21:10 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #395 (In Progress): [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- 21:10 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #395 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- 21:06 Tomas Tech Co.,Ltd. Sales support #394 (Closed): OTICS (Thailand) Company Limited meeting about IoT system and site servey
- 21:06 Tomas Tech Co.,Ltd. Sales support #394 (Closed): OTICS (Thailand) Company Limited meeting about IoT system and site servey
- 21:04 ACME INDUSTRY CO.,LTD. Project progress work #393 (Closed): Meeting with ACME INDUSTRY CO.,LTD and site survey and teaching for customer
- 21:04 ACME INDUSTRY CO.,LTD. Project progress work #393 (In Progress): Meeting with ACME INDUSTRY CO.,LTD and site survey and teaching for customer
- 21:02 ACME INDUSTRY CO.,LTD. Project progress work #393 (Closed): Meeting with ACME INDUSTRY CO.,LTD and site survey and teaching for customer
- 21:02 ACME INDUSTRY CO.,LTD. Project progress work #393 (Closed): Meeting with ACME INDUSTRY CO.,LTD and site survey and teaching for customer
- 21:00 Tomas Tech Co.,Ltd. Sales support #392 (Closed): Meeting at 25th Jan
- 20:59 Tomas Tech Co.,Ltd. Sales support #392 (Closed): Meeting at 25th Jan
- YAMATO ELECTRIC (THAILAND) CO.,LTD. meeting about Lock system at Ayuttaya
Topre (Thailand) Co., Ltd. meeting at Topre - 20:55 Tomas Tech Co.,Ltd. Sales support #391 (Closed): Meeting at 24th Jan
- 20:55 Tomas Tech Co.,Ltd. Sales support #391 (Closed): Meeting at 24th Jan
- TOKYO SANGYO (THAILAND) CO.,LTD. Oka meeting at MS teams
Siam Denso manufacturing meeting at SDM office
MAS-T pick... - 20:51 Tomas Tech Co.,Ltd. Sales support #390 (Closed): Meeting with Wing arc and Nakamura Kikho
- 20:50 Tomas Tech Co.,Ltd. Sales support #390 (Closed): Meeting with Wing arc and Nakamura Kikho
- 20:48 Tomas Tech Co.,Ltd. Sales support #389 (In Progress): THAI MATTO NS CO., LTD. proposal for Pegasus
- 20:47 Tomas Tech Co.,Ltd. Sales support #389 (In Progress): THAI MATTO NS CO., LTD. proposal for Pegasus
- 20:36 Sekiden (Thailand)Co.,Ltd. Sales support #388 (Closed): Proposal meeting at Sekiden
- 20:36 Sekiden (Thailand)Co.,Ltd. Sales support #388 (Closed): Proposal meeting at Sekiden
- Currently, the work performed by Mizuno has been simplified by Kuroda. We are solving this problem using Excel.
- 20:33 Tomas Tech Co.,Ltd. Sales support #387 (In Progress): Samurai asia film movie and interview
- 20:33 Tomas Tech Co.,Ltd. Sales support #387 (Closed): Samurai asia film movie and interview
- 20:29 Tomas Tech Co.,Ltd. Sales support #386 (Closed): Webseminar 2024/2/15
- 20:29 Tomas Tech Co.,Ltd. Sales support #374 (Closed): Meeting with CCI Automotive and proposal IoT system for Tank
- 17:19 Isuzu Engine Manufacturing Co.,(Thailand) Ltd. Project progress work #309 (In Progress): [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod
- develop Traceability system Line MC25&MC26.
- 16:48 NTPT Company Limited. Project progress work #385 (Close request): NTPT Asprova introduce and demo meeting
- 16:48 NTPT Company Limited. Project progress work #385 (Closed): NTPT Asprova introduce and demo meeting
26 Jan 2024
- 17:19 Minebea AccessSolutions Thai Ltd Project progress work #96 (Close request): [Internal Design] DB and various functions, man-hour calculation
- 17:05 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
- Develop Inner packing screen function C#.
25 Jan 2024
- 17:00 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
- Develop Inner packing screen function C#.
% Done 75 %
24 Jan 2024
- 16:51 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
- Develop Inner packing screen function C#.
- 16:33 Ebisu Foods Co Ltd. Project progress work #384 (Close request): meeting on site
- 15:29 Ebisu Foods Co Ltd. Project progress work #384 (Confirmation request): meeting on site
- 15:27 Ebisu Foods Co Ltd. Project progress work #384 (In Progress): meeting on site
- 15:27 Ebisu Foods Co Ltd. Project progress work #384 (Closed): meeting on site
- meeting on site for tacking in progress
- 16:33 Ebisu Foods Co Ltd. Project progress work #383 (Close request): Develop modify the master management module
- 16:18 Ebisu Foods Co Ltd. Project progress work #383 (Confirmation request): Develop modify the master management module
- 15:23 Ebisu Foods Co Ltd. Project progress work #383 (In Progress): Develop modify the master management module
- 15:22 Ebisu Foods Co Ltd. Project progress work #383 (Confirmation request): Develop modify the master management module
- 15:22 Ebisu Foods Co Ltd. Project progress work #383 (In Progress): Develop modify the master management module
- 15:21 Ebisu Foods Co Ltd. Project progress work #383: Develop modify the master management module
- Add Location and Business Partner to the menu
- 16:33 Tomas Tech Co.,Ltd. Project progress work #377 (Close request): Demo Dashboard CKD Pressure monitor
- 16:33 Tomas Tech Co.,Ltd. Sales support #315 (Close request): Shimizu correct 2 machines data from Takamatsu Mazak and sumaraize concept 27th
- 15:36 Ebisu Foods Co Ltd. Project progress work #16: WMS Web Development
- create action plan and diagram
- 15:31 Ebisu Foods Co Ltd. Project progress work #16: WMS Web Development
- transfer issue
23 Jan 2024
- 16:53 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
- Develop Inner packing screen function C#.
% Done 65 % - 16:20 Minebea AccessSolutions Thai Ltd Project progress work #381 (In Progress): [Coding]Android handyterminal BTA500 Outbound
- 10:20 Minebea AccessSolutions Thai Ltd Project progress work #381 (Closed): [Coding]Android handyterminal BTA500 Outbound
- Outbound ,Qc
- 15:45 Ebisu Foods Co Ltd. Project progress work #383 (Closed): Develop modify the master management module
- Leand and customize the menu to include functions related to business partners and hide the menu items related to cus...
- 10:23 Nidec Techno Motor (Thailand) Co.,Ltd. Problem-Bug #382 (Closed): Label format vietnam
- fix
22 Jan 2024
- 16:54 A.N.I. LOGISTICS, LTD. Project progress work #130: [Coding]Inner packing screen function C#
- Develop Inner packing screen function C#.
- 15:55 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #380 (Closed): Support And Fix
- Support And Fix
- 15:37 ACME INDUSTRY CO.,LTD. Project progress work #379 (Closed): support ACME INDUSTRY CO.,LTD.
- support
- 15:27 Ebisu Foods Co Ltd. Project progress work #378 (Closed): support Ebisu
- meeting
- 09:39 Tomas Tech Co.,Ltd. Project progress work #377 (Confirmation request): Demo Dashboard CKD Pressure monitor
- Demo Dashboard CKD Pressure monitor.
- 08:30 Tomas Tech Co.,Ltd. Project progress work #377: Demo Dashboard CKD Pressure monitor
- Demo Dashboard CKD Pressure monitor
- 08:13 Tomas Tech Co.,Ltd. Project progress work #377 (Closed): Demo Dashboard CKD Pressure monitor
- Demo Dashboard CKD Pressure monitor.
- 08:33 Tomas Tech Co.,Ltd. Sales support #315 (Confirmation request): Shimizu correct 2 machines data from Takamatsu Mazak and sumaraize concept 27th
- Shimizu correct 2 machines data from Takamatsu Mazak and sumaraize concept 27th
- 08:31 Tomas Tech Co.,Ltd. Sales support #315: Shimizu correct 2 machines data from Takamatsu Mazak and sumaraize concept 27th
- Shimizu correct 2 machines data from Takamatsu Mazak and sumaraize concept 27th
- 08:14 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #356 (Close request): Checking Process.
- 08:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #349 (Close request): Test WiFi data transmission between PLC to PLC
- 08:14 Tomas Tech Co.,Ltd. Project progress work #308 (Close request): Review and learn the source code of the project.