Activity
From 20 Oct 2023 to 29 Oct 2023
29 Oct 2023
- 11:26 Asian Stanley. International Limited 1.00 hour (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
- 11:09 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #10 (Closed): Creating a specification document)
- 11:09 Minebea AccessSolutions Thai Ltd 10.00 hours (Project progress work #10 (Closed): Creating a specification document)
27 Oct 2023
- 17:53 Nidec Techno Motor (Thailand) Co.,Ltd. 8.00 hours (Problem-Bug #153 (Closed): HTA_NSET completion fix bug.)
- 16:13 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #155 (Closed): Redmine Line Notify Software.)
- 10:08 Asian Stanley. International Limited 1.00 hour (Sales support #36 (Closed): UPS can not use in some position at LINE model H9J )
- 09:52 Asian Stanley. International Limited 1.00 hour (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
- 09:50 Tomas Tech Co.,Ltd. 1.00 hour (Sales support #46 (In Progress): Safety training adjustment)
26 Oct 2023
- 18:45 Nidec Techno Motor (Thailand) Co.,Ltd. 4.00 hours (Project progress work #154 (Closed): Warehouse automation system introduce)
- 18:44 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #10 (Closed): Creating a specification document)
- 17:57 Nidec Techno Motor (Thailand) Co.,Ltd. 5.00 hours (Problem-Bug #153 (Closed): HTA_NSET completion fix bug.)
- 17:50 Nidec Techno Motor (Thailand) Co.,Ltd. 3.00 hours (Project progress work #55 (Closed): handy terminal BT-A500 coding with Java Android.)
- 17:15 Asian Stanley. International Limited 4.00 hours (Problem-Bug #152 (Closed): Found the incorrect barcode generated)
- Modify the print label app and released the new version 2.2.4
- 16:06 Tomas Tech Co.,Ltd. 6.00 hours (Project progress work #144 (Closed): PLC alarm record and send to wdt-clients2.)
- 13:36 Asian Stanley. International Limited 8.00 hours (Project progress work #59 (Closed): Support installation HT-Label printing system)
- 11:35 ATA Casting Technology Co., Ltd. 1.00 hour (Project progress work #149 (Closed): Request to test the modified with new packing app)
- 10:30 ATA Casting Technology Co., Ltd. 2.00 hours (Project progress work #149 (Closed): Request to test the modified with new packing app)
- Test.
- 11:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 2.00 hours (Project progress work #143 (Closed): Production IoT project requirements and support project)
- 11:15 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 1.00 hour (Project progress work #143 (Closed): Production IoT project requirements and support project)
25 Oct 2023
- 16:55 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #144 (Closed): PLC alarm record and send to wdt-clients2.)
- 16:43 Ebisu Foods Co Ltd. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
- 12:24 Siam Denso Manufacturing Co.,Ltd. 8.00 hours (Problem-Bug #78 (Closed): Found problem about the alarm of sequnce)
- 12:18 Asian Stanley. International Limited 8.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
- 12:18 Tomas Tech Co.,Ltd. 10.00 hours (Sales support #45 (Closed): PTL DEMO kit concept for murata)
- 12:11 Asian Stanley. International Limited 8.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
24 Oct 2023
- 21:42 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 10.00 hours (Project progress work #143 (Closed): Production IoT project requirements and support project)
- 21:40 ACME INDUSTRY CO.,LTD. 10.00 hours (Project progress work #142 (Closed): UAT about the WMS system and onsite support)
- 19:45 Asian Stanley. International Limited 8.00 hours (Project progress work #59 (Closed): Support installation HT-Label printing system)
- 16:45 Ebisu Foods Co Ltd. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
- 16:06 Asteer (Thailand) Co., Ltd. 8.00 hours (Project progress work #21 (Closed): Handy terminal application system Development.)
23 Oct 2023
- 21:15 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #10 (Closed): Creating a specification document)
- 21:14 A.N.I. LOGISTICS, LTD. 6.00 hours (Sales support #62 (Closed): CKD project phase3 Proposal activities + requirements definition)
21 Oct 2023
- 17:46 Nidec Techno Motor (Thailand) Co.,Ltd. 8.00 hours (Problem-Bug #138 (Closed): HTA_NSET completion fix bug.)
- 15:29 Shodensha (Thailand) Co., Ltd. 4.00 hours (Problem-Bug #60 (Closed): Procedure manual application development modifictaion problem)
- 13:38 Asian Stanley. International Limited 8.00 hours (Project progress work #59 (Closed): Support installation HT-Label printing system)
- 09:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 2.00 hours (Sales support #57 (Closed): Production IoT project requirements definition)
- Meeting with Kishio san and exprain about wiring problem
- 09:32 ADVICS Manufacturing(Thailand)Co.,Ltd. 2.00 hours (Project progress work #12 (Closed): Addition function display)
- Site check with Keyence Kobayashi and Uchikoshi
- 09:31 Mitsui Precision Thai Co.,Ltd 4.00 hours (Sales support #137 (Closed): Sales and presentation about Pegasus production management system)
- meeting with Nakajima and Tokutome MD
20 Oct 2023
- 18:36 Ebisu Foods Co Ltd. 8.00 hours (Project progress work #17 (Closed): WMS handy terminal BT-A500 coding with Java Android.)
- 17:12 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
- Modify the web and DB schema to mapping the item to supplier ID and add the uncontrol flag for all items. Create the ...
- 16:14 Shodensha (Thailand) Co., Ltd. 8.00 hours (Problem-Bug #60 (Closed): Procedure manual application development modifictaion problem)
- 13:49 Tomas Tech Co.,Ltd. 5.00 hours (Sales support #24 (Closed): [FY2023]Common management for Ryo Nozaki)
- Redmine check and make issue
- 13:48 Asian Stanley. International Limited 4.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
- Check site
- 07:40 Asian Stanley. International Limited 8.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
Also available in: Atom