Activity
From 13 Feb 2024 to 22 Feb 2024
22 Feb 2024
- 16:35 Project progress work #451 (In Progress): Water treatment.
- 16:33 Project progress work #451 (Closed): Water treatment.
- Check equipment price compare from supplier ..
Design drawing
21 Feb 2024
- 19:14 Project progress work #201 (Closed): Summary of all equipment for use in the Machine operation monitoring systems project.
- 19:14 Sales support #175 (Closed): EV charger installation project
- 19:14 Project progress work #422 (Closed): Install PLC programs
- 19:14 Project progress work #438 (Closed): Survery Essilor manufacturing
- 19:14 Project progress work #437 (Closed): support ANI
20 Feb 2024
- 08:50 Project progress work #438 (Close request): Survery Essilor manufacturing
- 08:50 Project progress work #437 (Close request): support ANI
13 Feb 2024
- 19:47 Project progress work #438 (Confirmation request): Survery Essilor manufacturing
- Survery Essilor manufacturing
- 19:46 Project progress work #438 (Closed): Survery Essilor manufacturing
- Survery Essilor manufacturing
- 19:41 Project progress work #437 (Confirmation request): support ANI
- On-site support at ANI
- 19:38 Project progress work #437 (Closed): support ANI
- On-site support at ANI
Also available in: Atom