Project

General

Profile

Activity

From 08 Feb 2024 to 17 Feb 2024

13 Feb 2024

19:47 Project progress work #438 (Confirmation request): Survery Essilor manufacturing
Survery Essilor manufacturing Suthiwat Banrueangthong
19:46 Project progress work #438 (Closed): Survery Essilor manufacturing
Survery Essilor manufacturing Suthiwat Banrueangthong
19:41 Project progress work #437 (Confirmation request): support ANI
On-site support at ANI Suthiwat Banrueangthong
19:38 Project progress work #437 (Closed): support ANI
On-site support at ANI Suthiwat Banrueangthong

08 Feb 2024

15:42 Project progress work #434 (In Progress): [ Specicication and document ] for Water treatment project
Nattapol Poeam
15:42 Project progress work #434: [ Specicication and document ] for Water treatment project
[ Next Acction ]
Site survey 11/02/24
- Expain concept and point installation sensor to SND Team.
- Water flow met...
Nattapol Poeam
15:34 Project progress work #434 (Closed): [ Specicication and document ] for Water treatment project
- Schedule
- Sub Schedule
- Specification
- Data document
Nattapol Poeam
 

Also available in: Atom