Activity
From 08 Feb 2024 to 17 Feb 2024
13 Feb 2024
- 19:47 Project progress work #438 (Confirmation request): Survery Essilor manufacturing
- Survery Essilor manufacturing
- 19:46 Project progress work #438 (Closed): Survery Essilor manufacturing
- Survery Essilor manufacturing
- 19:41 Project progress work #437 (Confirmation request): support ANI
- On-site support at ANI
- 19:38 Project progress work #437 (Closed): support ANI
- On-site support at ANI
08 Feb 2024
- 15:42 Project progress work #434 (In Progress): [ Specicication and document ] for Water treatment project
- 15:42 Project progress work #434: [ Specicication and document ] for Water treatment project
- [ Next Acction ]
Site survey 11/02/24
- Expain concept and point installation sensor to SND Team.
- Water flow met... - 15:34 Project progress work #434 (Closed): [ Specicication and document ] for Water treatment project
- - Schedule
- Sub Schedule
- Specification
- Data document