Project

General

Profile

Activity

From 01 Feb 2024 to 10 Feb 2024

08 Feb 2024

15:42 4.00 hours (Project progress work #434 (Closed): [ Specicication and document ] for Water treatment project)
Schedule and Sub Schedule Nattapol Poeam
08:09 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
Design signals that require Plant B along with design Suthiwat Banrueangthong

07 Feb 2024

22:28 8.00 hours (Project progress work #87 (Closed): IoT Equipment for machine operation project)
Revised data memory Nattapol Poeam

06 Feb 2024

16:29 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
Power on TB-Box Plant A and Data monitor from Machine Spiral Nattapol Poeam
16:27 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
Monitoring and communication test on Plant A Nattapol Poeam
15:57 8.00 hours (Project progress work #422 (Closed): Install PLC programs )
Install programs for PLC and HMI Suthiwat Banrueangthong
15:55 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
Test PLC signal reception Suthiwat Banrueangthong

04 Feb 2024

20:20 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
Run the cable from the ceiling down to the plantB machine. Suthiwat Banrueangthong
20:18 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
Finished wiring from the ceiling down to all plantB machines and installing plc connection equipment. Suthiwat Banrueangthong

03 Feb 2024

08:55 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
Set all required bits in plant A Suthiwat Banrueangthong
08:43 4.00 hours (Project progress work #417 (Closed): Go solve problems on site at TNF.)
Solve the problem of machines not working at TNF Suthiwat Banrueangthong

02 Feb 2024

09:32 4.00 hours (Sales support #86 (Closed): IoT Equipment for Water treatment project)
Summarize equipment and check spec device Nattapol Poeam

01 Feb 2024

19:12 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
design machine Polystar Suthiwat Banrueangthong
08:10 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
Design main program Suthiwat Banrueangthong
08:49 8.00 hours (Project progress work #422 (Closed): Install PLC programs )
Install PLC programs kv studio,vt studio,GX-Work2,gt designer 3 Suthiwat Banrueangthong
08:45 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
Go to support at TNF Suthiwat Banrueangthong
08:24 4.00 hours (Project progress work #417 (Closed): Go solve problems on site at TNF.)
Go solve problems on site at TNF. Suthiwat Banrueangthong
 

Also available in: Atom