Activity
From 25 Jan 2024 to 03 Feb 2024
03 Feb 2024
- 08:55 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set all required bits in plant A
- 08:43 4.00 hours (Project progress work #417 (Closed): Go solve problems on site at TNF.)
- Solve the problem of machines not working at TNF
02 Feb 2024
- 09:32 4.00 hours (Sales support #86 (Closed): IoT Equipment for Water treatment project)
- Summarize equipment and check spec device
01 Feb 2024
- 19:12 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- design machine Polystar
- 08:10 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Design main program
- 08:49 8.00 hours (Project progress work #422 (Closed): Install PLC programs )
- Install PLC programs kv studio,vt studio,GX-Work2,gt designer 3
- 08:45 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Go to support at TNF
- 08:24 4.00 hours (Project progress work #417 (Closed): Go solve problems on site at TNF.)
- Go solve problems on site at TNF.
31 Jan 2024
- 19:36 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Installation AMX PLC to Polystar machine
- 19:24 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- design dashboard Spiral machine
- 19:23 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit of the Spiral machine.
- 19:23 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit of the Spiral machine.
- 19:19 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- summax machine design
- 19:18 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the bit that must be used by the summax machine.
- 19:16 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Hi-cook machine design completed
- 19:15 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Hicook machine design
- 19:14 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- H-icook machine design
- 19:11 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit for each machine.
- 19:11 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Set the required bit for each machine.
- 19:10 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Start designing the main
- 19:08 4.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Start designing the main
- 19:01 8.00 hours (Project progress work #400 (Closed): Program developer and Dashboard design)
- Organize the dashboard concept
- 19:20 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Route the I/O cables on the ceiling to the machine location.
- 19:13 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Wiring the ceiling from the plantB cabinet
- 19:06 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- config machinery and ceiling drilling Plant A
- 19:05 8.00 hours (Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF)
- config machinery and ceiling drilling Plant A
30 Jan 2024
- 21:08 8.00 hours (Project progress work #403 (Closed): Summarize equipment of Water treatment project)
- Summarize equipment
- 20:55 4.00 hours (Sales support #86 (Closed): IoT Equipment for Water treatment project)
- Site survey
- 20:44 4.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- On-site to support problem machine brakedown
- 20:36 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- On-site support after installation module PLC of Polystar
- 20:27 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Installation TB-Box in Plant A
- 20:26 8.00 hours (Project progress work #243 (Closed): [ Task ] Program design and development )
- Program design
Also available in: Atom