25 Dec 2023
- 21:31 2.00 hours (Project progress work #243 (Closed): [ Task ] Program design and development )
- Program design
- 21:26 7.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Prepare equipment
- 21:25 1.00 hour (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Prepare equipment
24 Dec 2023
- 15:46 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Installation TB-Box 1 and TB-Box 2 in Plant B
- 15:44 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Prepare equipment and make drawing I/O for explain FN TECH Team connect to machine
- 15:24 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Installation TB-Box1 plant A
- 14:56 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Installation TB-Box 2 in plant A
- 14:55 8.00 hours (Project progress work #243 (Closed): [ Task ] Program design and development )
- Design and prepare equipment for installation TB-Box