Activity
From 15 Nov 2023 to 24 Nov 2023
24 Nov 2023
- 16:47 8.00 hours (Project progress work #248 (Closed): Check List Equipment for Install in Cabinet)
- Install equipment in control box 2set total 4 set finish. Next week wiring continues.
23 Nov 2023
- 16:53 8.00 hours (Project progress work #248 (Closed): Check List Equipment for Install in Cabinet)
- Install equipment in control box 2set.
22 Nov 2023
- 17:01 8.00 hours (Project progress work #248 (Closed): Check List Equipment for Install in Cabinet)
- 08:38 4.00 hours (Project progress work #243 (Closed): [ Task ] Program design and development )
- Program design
21 Nov 2023
- 17:02 8.00 hours (Project progress work #248 (Closed): Check List Equipment for Install in Cabinet)
- Go to Bitec Bang-na at 1:00 Pm. With Mr.Santi &Mr.Nattapol for the setting demo PLC.
20 Nov 2023
18 Nov 2023
- 17:22 6.00 hours (Project progress work #243 (Closed): [ Task ] Program design and development )
- Program design
17 Nov 2023
- 16:56 8.00 hours (Project progress work #87 (Closed): IoT Equipment for machine operation project)
- Prorgam design
- 16:55 8.00 hours (Project progress work #220 (Closed): Design drawing and confirm equipment)
16 Nov 2023
15 Nov 2023