Activity
From 09 Nov 2023 to 18 Nov 2023
18 Nov 2023
- 17:53 Project progress work #242 (Close request): Program design and development
- 17:21 Project progress work #242 (Confirmation request): Program design and development
- Please delete this issue because it was created incorrectly. krub
- 17:14 Project progress work #242 (Closed): Program design and development
- Program design and development
- PLC
- Dashboard - 17:53 Project progress work #220 (Close request): Design drawing and confirm equipment
- 17:23 Project progress work #243 (In Progress): [ Task ] Program design and development
- 17:19 Project progress work #243 (Closed): [ Task ] Program design and development
- Program design and development
- PLC
- Dashboard
17 Nov 2023
- 16:56 Project progress work #87: IoT Equipment for machine operation project
- - Pick up your equipment at TNF.
- Design data from machine and I/O - 16:55 Project progress work #220 (Confirmation request): Design drawing and confirm equipment
14 Nov 2023
- 13:28 Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project.
- List equipment of TNF_PJ230043
https://drive.google.com/drive/folders/1RhnGOBfTuZGQImPFWH4omgd_8RDj5-Ir?usp=drive_li...
13 Nov 2023
- 17:11 Sales support #175: EV charger installation project
- Next action
> Support customer
> Wait PO
10 Nov 2023
- 16:52 Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project.
- Summarize equipment before order and requst a quotation supplier
09 Nov 2023
- 17:12 Project progress work #220 (In Progress): Design drawing and confirm equipment
- 17:09 Project progress work #220 (Closed): Design drawing and confirm equipment
- Design drawing
- TB Box
- I/O
Also available in: Atom