06 Nov 2023
- 19:30 5.00 hours (Project progress work #201 (Closed): Summary of all equipment for use in the Machine operation monitoring systems project.)
- Revise and summarize all equipment of the Machine operation monitoring system project.
- 17:28 4.00 hours (Sales support #175 (Closed): EV charger installation project)
- Site survey 06/11/23
04 Nov 2023
- 14:14 8.00 hours (Project progress work #87 (Closed): IoT Equipment for machine operation project)
- Update document layout plant
- 14:08 8.00 hours (Sales support #175 (Closed): EV charger installation project)
- Update document about installation EV-Charger
- 14:06 8.00 hours (Sales support #175 (Closed): EV charger installation project)
- Update document about installation EV-Charger
02 Nov 2023
- 17:17 4.00 hours (Project progress work #87 (Closed): IoT Equipment for machine operation project)
- 08:44 8.00 hours (Project progress work #87 (Closed): IoT Equipment for machine operation project)
- Document specification update R2 of the project Machine operation monitoring system specifications.