Hours: 1105.50

Date User Activity Issue Comment Hours
16 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Export PDF Label Production Lot Size. 8.00 Actions
16 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Inbound material. 8.00 Actions
16 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Add API Outbound. 8.00 Actions
15 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Import Delivery Schedule Pokayoke 8.00 Actions
13 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Inbound delivery Note And Inbound Material PO 8.00 Actions
13 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Add data to inbound deliverynote. 8.00 Actions
12 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Import Production Schedule SDI 8.00 Actions
12 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Inbound function. 8.00 Actions
11 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed additional client requirements for schedule_perchasorder_delivery and schedule_tag_supplier. 8.00 Actions
11 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Inbound. 8.00 Actions
10 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Develop schedule_perchasorder_delivery and schedule_tag_supplier as per additional client requirements; currently working on schedule_perchasorder_delivery. 5.00 Actions
10 Jul 2024 Ronnagon Kongsuwan Meeting Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Attend meeting and gather additional requirements from the client. 3.00 Actions
10 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and develop 8.00 Actions
09 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Export PDF Label Supplier Information download 3 files pdf in oneclick. 8.00 Actions
09 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Stock function. 8.00 Actions
08 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Export PDF Label Supplier Information. 8.00 Actions
08 Jul 2024 Taweesak Prumvised Make document Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Created API Document and meeting overall function. 8.00 Actions
05 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Add inbound items page. 8.00 Actions
05 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Export PDF Delivery Note. 8.00 Actions
05 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Add API Inbound schedule coil. 8.00 Actions
04 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Export PDF Delivery Note. 8.00 Actions
03 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Export PDF Purchase Order. 8.00 Actions
02 Jul 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Develop and design a PDF export feature for perches orders and build an API for scheduling inbound tasks. 8.00 Actions
02 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Set API Inbound. 8.00 Actions
01 Jul 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Edit UI of Stock function. 8.00 Actions