21 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Installation software on site. 8.00 Actions
20 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Final test on the web and handy presentation with the client, and bug fixing. 8.00 Actions
20 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Testing and meeting present with TMC. 8.00 Actions
19 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Internal test with handy and fix bug 8.00 Actions
19 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 7.00 Actions
16 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 8.00 Actions
16 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Production PartRequest And Test Inbound Production cut material in bom type lotsize and production sdi 8.00 Actions
15 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Production Bom Fg,SDI,FG and SDI Test Outbound delivery 8.00 Actions
15 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Test and fixed outbound and lotsize function. 4.00 Actions
14 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Test and fixed bug Outbound delivery 5.00 Actions
14 Aug 2024 Ronnagon Kongsuwan Meeting Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Meeting with tmc finish design bom and preview web pegasus 3.00 Actions
14 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Test outbound delivery and meeting with TMC. 3.00 Actions
13 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Inbound Schedule Production SDI - Outbound Material By Bom Test Delivery Outbound Schedule 8.00 Actions
13 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 4.00 Actions
10 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Inbound Schedule Production Fg - Outbound Material By Bom 8.00 Actions
10 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 5.00 Actions
09 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 2.00 Actions
09 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed stored procedures for BOM in inbound to manage outbound material and fixed bugs in the inbound material PO stored procedure. 8.00 Actions
08 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed table Bom Page Bom in master data 8.00 Actions
07 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Test Fix bug Function Inbound Schedule Material 8.00 Actions
07 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Development. 8.00 Actions
06 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed 3 Approved function schedule inbound permission generate pdf 8.00 Actions
06 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Development. 8.00 Actions
05 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and develop. 8.00 Actions
05 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed New Design Page Outbound Schedule Delivery Manual Generate New requirement client. 8.00 Actions