21 Oct 2024

08:39 8.00 hours (Project progress work #750 (Closed): Fixed function Web Pegasus after training.)
Developed and completed Fix error inbound and the adjustment of DN(Delivery Note) PDF printing to dynamically suppor... Ronnagon Kongsuwan
08:03 1.00 hour (Project progress work #741 (Closed): Fixed function after training.)
Support fixed bugs inbound. Taweesak Prumvised

17 Oct 2024

16:08 8.00 hours (Project progress work #750 (Closed): Fixed function Web Pegasus after training.)
Developed and completed the adjustment of PO PDF printing to dynamically support multiple part pages after real-world... Ronnagon Kongsuwan
16:00 4.00 hours (Project progress work #750 (Closed): Fixed function Web Pegasus after training.)
Remotely cleared test data and erroneous inbound records on Handdy to perform a new inbound on the live server. Ronnagon Kongsuwan
15:56 8.00 hours (Project progress work #750 (Closed): Fixed function Web Pegasus after training.)
Developed and completed the revision of the import schedule function to include error notifications and redesigned it... Ronnagon Kongsuwan

16 Oct 2024

16:44 3.00 hours (Project progress work #741 (Closed): Fixed function after training.)
Support fixed issues after test. Taweesak Prumvised
 