02 Aug 2024

18:11 3.00 hours (Project progress work #604 (Closed): [Coding] Warehouse management system handyterminal Java Phase01)
Update progress. Taweesak Prumvised
17:28 8.00 hours (Project progress work #668 (Closed): Upgrade web interface)
# Inbound - Inbound Inquiry / Report, # Outbound - Outbound Inquiry / Report Worawit Khantamool
12:08 3.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Meeting progress web pegasus and new requirement bom with client. Ronnagon Kongsuwan
12:07 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Developed Page Pokayoke. Ronnagon Kongsuwan

01 Aug 2024

16:43 8.00 hours (Project progress work #668 (Closed): Upgrade web interface)
# Stock Management - Tag Label (100%) Worawit Khantamool

31 Jul 2024

17:58 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Developed and completed the generation of PDF packing list pages for scheduled outbound deliveries. Ronnagon Kongsuwan
16:44 8.00 hours (Project progress work #668 (Closed): Upgrade web interface)
# Stock Management - Stock Maintenance Inquiry / Report, Tag Label (50%) Worawit Khantamool

30 Jul 2024

16:41 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Developed and completed manual generate schedule outbound delivery table. Ronnagon Kongsuwan
16:39 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Developed New Design Page Outbound Schedule Delivery Manual Generate New requirement client. Ronnagon Kongsuwan

27 Jul 2024

16:54 8.00 hours (Project progress work #604 (Closed): [Coding] Warehouse management system handyterminal Java Phase01)
Check function and document. Taweesak Prumvised

26 Jul 2024

17:21 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Developed and completed Page Inbound Schedule Production fg/sdi and table result view details and gen pdf lotsize. Ronnagon Kongsuwan
17:03 8.00 hours (Project progress work #668 (Closed): Upgrade web interface)
# Stock Management -Change Location, - Stocktaking Worawit Khantamool
16:53 8.00 hours (Project progress work #604 (Closed): [Coding] Warehouse management system handyterminal Java Phase01)
Edit code. Taweesak Prumvised

25 Jul 2024

19:47 0.00 hour (Project progress work #621 (Closed): Meeting)
Soraya Norasing
16:58 8.00 hours (Project progress work #668 (Closed): Upgrade web interface)
# Stock Management - Stock Inquiry / Report, - Stock Maintenance Worawit Khantamool
16:45 8.00 hours (Project progress work #604 (Closed): [Coding] Warehouse management system handyterminal Java Phase01)
Meeting and develop. Taweesak Prumvised
16:37 2.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Meeting progress web pegasus with client. Ronnagon Kongsuwan
16:35 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Developed and completed PDF generation to include order number and perches order as per customer requirements. Ronnagon Kongsuwan
16:31 8.00 hours (Project progress work #650 (Closed): [Coding] Warehouse management system Web App PHP Pegasus Phase1)
Developed and completed new page design inbound schedule material and gen pdf 3 files. Ronnagon Kongsuwan
 