Estimated time: 1152.00 Spent time: 72.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
2797 Project progress work New Normal [Coding] Pre-Blend Surat Duangchiaw 16.00 0.00 24 Dec 2025 13:40 Actions
2796 Project progress work New Normal [Coding] OM-Mixer Surat Duangchiaw 16.00 0.00 24 Dec 2025 13:40 Actions
1681 Project progress work New Normal [Coding] Weighing Surat Duangchiaw 16.00 0.00 24 Dec 2025 13:41 Actions
3387 Project progress work New Normal [Coding] Process control Surat Duangchiaw 0.00 24 Dec 2025 13:49 Actions
3353 Project progress work New Normal [Installation&On-site support] Onsite support Surat Duangchiaw 0.00 26 Dec 2025 17:15 Actions
1580 Project progress work In Progress Normal [Coding] BOM Designer and Revision control Thiraporn Amornsirinukorh 40.00 0.00 12 Nov 2025 16:52 Actions
2884 Project progress work In Progress Normal [Coding] Production Schedule - Backend Thiraporn Amornsirinukorh 16.00 56.00 13 Dec 2025 11:02 Actions
2997 Project progress work New Normal [Coding] Production Planning (Work Instruction Sheet) Thiraporn Amornsirinukorh 32.00 0.00 24 Dec 2025 17:06 Actions
3381 Project progress work New Normal [Coding] Color matching Backend Thiraporn Amornsirinukorh 0.00 24 Dec 2025 13:31 Actions
3380 Project progress work New Normal [Coding] Color matching Frontend Thiraporn Amornsirinukorh 16.00 0.00 24 Dec 2025 13:30 Actions
1706 Project progress work New Normal [Coding] Dashboard report – Production monitoring Thiraporn Amornsirinukorh 16.00 0.00 13 Dec 2025 11:10 Actions
3351 Project progress work New Normal [Installation&On-site support] Onsite support Thiraporn Amornsirinukorh 0.00 26 Dec 2025 17:15 Actions