Estimated time: 104.00 Spent time: 56.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
2997 Project progress work New Normal [Coding] Production Planning (Work Instruction Sheet) Thiraporn Amornsirinukorh 32.00 0.00 13 Dec 2025 11:02 Actions
2884 Project progress work In Progress Normal [Coding] Production Schedule - Backend Thiraporn Amornsirinukorh 16.00 56.00 13 Dec 2025 11:02 Actions
1706 Project progress work New Normal [Coding] Dashboard report – Production monitoring Thiraporn Amornsirinukorh 16.00 0.00 13 Dec 2025 11:10 Actions
1580 Project progress work In Progress Normal [Coding] BOM Designer and Revision control Thiraporn Amornsirinukorh 40.00 0.00 12 Nov 2025 16:52 Actions
    (1-4/4)