Estimated time: 192.00 Spent time: 96.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
6999 Project progress work New Normal [Coding] Blender, extrudig return Taweesak Prumvised 88.00 0.00 18 Mar 2026 14:53 Actions
6479 Project progress work New Normal [Coding] Blender Pokayoke Taweesak Prumvised 0.00 10 Feb 2026 08:25 Actions
3286 Project progress work New Normal [Coding] Injection Taweesak Prumvised 8.00 0.00 10 Feb 2026 08:38 Actions
2802 Project progress work New Normal [Coding] Extruding WIP Return Taweesak Prumvised 8.00 0.00 10 Feb 2026 08:32 Actions
2801 Project progress work New Normal [Coding] Blender RM Return Taweesak Prumvised 16.00 16.00 10 Feb 2026 08:23 Actions
2799 Project progress work New Normal [Coding] Blender Preparation Record Taweesak Prumvised 32.00 32.00 10 Feb 2026 08:22 Actions
2798 Project progress work New Normal [Coding] Blender Process Taweesak Prumvised 16.00 16.00 10 Feb 2026 08:12 Actions
2795 Project progress work New Normal [Coding] Extruding Process Taweesak Prumvised 16.00 16.00 10 Feb 2026 08:27 Actions
1593 Project progress work New Normal [Coding] Extruding/Data Record Taweesak Prumvised 8.00 16.00 10 Feb 2026 08:31 Actions