Project

General

Profile

Gantt

Filters

Zoom in Zoom out « January | March »

months from Apply Clear

Parent project #900: [PJ240063] Production management system for Thai Matto NS wiring Option 1 - EMT
Project progress work #1596: [Coding] Software test
Project progress work #1555: [Coding] Master management
Project progress work #1580: [Coding] BOM Designer and Revision control
Project progress work #3284: [Coding] Quotation Master
Project progress work #1166: [Coding] Schedule
Project progress work #2884: [Coding] Production Schedule - Backend
Project progress work #2997: [Coding] Production Planning (Work Instruction Sheet)
Project progress work #3281: [Coding] PO Order FIX
Project progress work #3282: [Coding] PO Stock Order FIX
Project progress work #3283: [Coding] PO Merchandize Order FIX
Project progress work #1601: [Installation&On-site support]
Project progress work #1546: [Coding] Stock management
Project progress work #1706: [Coding] Dashboard report – Production monitoring
Project progress work #1581: [Coding] Handy development
Project progress work #1587: [Coding] Weighing API
Project progress work #2804: [Coding] Delivery
Project progress work #2802: [Coding] Extruding WIP Return
Project progress work #2803: [Coding] Packing
Project progress work #1681: [Coding] Weighing
Project progress work #2796: [Coding] OM-Mixer
Project progress work #2797: [Coding] Pre-Blend
Project progress work #1594: [Coding] i-Reporter development

Status

In Progress
In Progress
In Progress
In Progress
New
In Progress
In Progress
New
New
New
New
New
In Progress
New
New
New
New
New
New
New
New
New
New

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

2064.00
688.00
288.00
40.00
284.00
16.00
32.00
200.00
72.00
16.00
368.00
8.00
8.00
8.00
24.00
16.00
16.00
16.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Updated

13 Dec 2025 11:33
30 Oct 2025 09:47
13 Dec 2025 11:13
12 Nov 2025 16:52
13 Dec 2025 11:13
13 Dec 2025 11:15
13 Dec 2025 11:02
13 Dec 2025 11:02
13 Dec 2025 11:04
13 Dec 2025 11:05
13 Dec 2025 11:06
03 Nov 2025 16:49
13 Dec 2025 11:10
13 Dec 2025 11:10
13 Dec 2025 11:37
31 Oct 2025 14:56
13 Dec 2025 11:35
13 Dec 2025 11:37
13 Dec 2025 11:38
20 Nov 2025 11:23
13 Dec 2025 11:36
13 Dec 2025 11:36
13 Dec 2025 11:32
 
 
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Tomas Tech All Project Management
 
 
THAI MATTO NS CO.,LTD.
 
 
In Progress
Parent project #900: [PJ240063] Production management system for Thai Matto NS wiring Option 1 - EMT

Project: THAI MATTO NS CO.,LTD.
Status: In Progress
Start date: 09 Dec 2024
Due date: 08 Feb 2026
Assignee: Kittisak Isarapongporn
Priority: Normal
In Progress 50%
In Progress 93%
In Progress 90%
New 0%
In Progress 90%
In Progress 70%
New 60%
New 70%
New 70%
New 70%
 
New 0%
Project progress work #1601: [Installation&On-site support]

Project: THAI MATTO NS CO.,LTD.
Status: New
Start date: 03 Oct 2025
Due date: 08 Feb 2026
Assignee: Kittisak Isarapongporn
Priority: Normal
In Progress 90%
New 50%
New 94%
New 60%
New 50%
New 80%
New 90%
New 80%
New 80%
New 80%
New 100%