Project progress work #1596: [Coding] Software test Project progress work #1596: [Coding] Software test

Project: THAI MATTO NS CO.,LTD.
Status: In Progress
Start date: 01 Aug 2025
Due date: 28 Nov 2025
Assignee: Kittisak Isarapongporn
Priority: Normal

2

32

3

4

5

6

7

8

9

33

10

11

12

13

14

15

16

34

17

18

19

Project progress work #1555: [Coding] Master management Project progress work #1555: [Coding] Master management

Project: THAI MATTO NS CO.,LTD.
Status: In Progress
Start date: 19 Aug 2025
Due date: 17 Dec 2025
Assignee:
Priority: Normal

20

21

22

23

35

24

25

26

27

28

29

30

36

31

1

2

3

4

5

6

Project progress work #1166: [Coding] Schedule Project progress work #1166: [Coding] Schedule

Project: THAI MATTO NS CO.,LTD.
Status: In Progress
Start date: 06 Sep 2025
Due date: 16 Dec 2025
Assignee:
Priority: Normal