Project

General

Profile

Activity

From 27 May 2026 to 05 Jun 2026

29 May 2026

15:24 Project progress work #3353 (Closed): [Installation&On-site support] Onsite support
Waraporn Promsopa
15:24 Project progress work #3352 (Closed): [Installation&On-site support] Onsite support
Waraporn Promsopa
15:24 Project progress work #3351 (Closed): [Installation&On-site support] Onsite support
Waraporn Promsopa
15:24 Project progress work #8402 (Closed): [Installation&On-site support] Check AP connection
Waraporn Promsopa
15:23 Project progress work #8402 (Closed): [Installation&On-site support] Check AP connection
Waraporn Promsopa
11:07 Project progress work #8384 (Closed): [Installation&On-site support] Fix Network Ploblem
Waraporn Promsopa
11:07 Project progress work #8384 (Closed): [Installation&On-site support] Fix Network Ploblem
Waraporn Promsopa
11:04 Project progress work #8383 (Closed): [Requirement definition] รับ Requirement ของลูกค้า และตรวจสอบ Issue ของลูกค้า Extruding process
Waraporn Promsopa
11:04 Project progress work #8383 (Closed): [Requirement definition] รับ Requirement ของลูกค้า และตรวจสอบ Issue ของลูกค้า Extruding process
Waraporn Promsopa
11:03 Project progress work #8382 (Closed): [Requirement definition] รับ Requirement ของลูกค้า
Waraporn Promsopa
11:03 Project progress work #8382 (Closed): [Requirement definition] รับ Requirement ของลูกค้า
Waraporn Promsopa
11:00 Project progress work #8380 (Closed): [Coding] ทำ check list requiremet ของ Handy
Waraporn Promsopa
10:59 Project progress work #8380 (Closed): [Coding] ทำ check list requiremet ของ Handy
Waraporn Promsopa
 

Also available in: Atom