Activity
From 19 Nov 2025 to 28 Nov 2025
19 Nov 2025
- 09:10 Project progress work #2962: [Installation&On-site support] Connect and field test system
- 1 Connect the RS485 cable to loop 1 (air compressor)
2 Connect the RS485 loop 2 (inverter)
3 Air compressor field ... - 08:48 Project progress work #2962 (Closed): [Installation&On-site support] Connect and field test system
- 09:09 Project progress work #2961: [Installation&On-site support] Installation and wiring Air flow sensor
- 1 Wiring RS485 cable to Air flow sensor.
2 Wiring power 24VDC cable to Air flow sensor.
3 Installation Air flow se... - 08:47 Project progress work #2961 (Closed): [Installation&On-site support] Installation and wiring Air flow sensor
- 09:08 Project progress work #2960: [Installation&On-site support] Blower Exhaust cabinets old.
- 1 Wiring I/O Signal for Control Exhaust fan 13 Unit
2 Wiring I/O Signal for Control Cool jet fan 2 Unit
3 Wiring ... - 08:46 Project progress work #2960 (Closed): [Installation&On-site support] Blower Exhaust cabinets old.
- 09:07 Project progress work #2959: [Installation&On-site support] Installation and wiring cabinet Blower Exhaust new
- 1 Installation control cabinet.
2 Wiring power from Blower Exhaust cabinets old to new.
3 Wiring I/O Cable from Bl... - 08:45 Project progress work #2959 (Closed): [Installation&On-site support] Installation and wiring cabinet Blower Exhaust new
- 09:06 Project progress work #2958: [Installation&On-site support] Air Dryer 2 Units
- 1 Wiring and connect I/O Signal
2 I/O Check - 08:44 Project progress work #2958 (Closed): [Installation&On-site support] Air Dryer 2 Units
- 09:05 Project progress work #2957: [Installation&On-site support] Installation and wiring cabinet Utility Air compressor, Dryer
- 1 Installation control cabrinet
2 Wiring main power from old magnetic to new panel
3 Wiring signal I/O From mai... - 08:43 Project progress work #2957 (Closed): [Installation&On-site support] Installation and wiring cabinet Utility Air compressor, Dryer
- 09:04 Project progress work #2955: [Installation&On-site support] Installation and wiring LAN cables and RS485 cable of Utility
- 1 Installation and wiring LAN From main panel to Server room
2 Installation and wiring RS485 From main panel to Air... - 08:58 Project progress work #2955 (In Progress): [Installation&On-site support] Installation and wiring LAN cables and RS485 cable of Utility
- 08:41 Project progress work #2955 (Closed): [Installation&On-site support] Installation and wiring LAN cables and RS485 cable of Utility
- 08:40 Project progress work #2955 (Closed): [Installation&On-site support] Installation and wiring LAN cables and RS485 cable of Utility
- 08:58 Project progress work #2965 (Closed): [Installation&On-site support] Installation and Configuration Production system
- 08:53 Project progress work #2964 (Closed): [Installation&On-site support] System utility integration test
- 08:50 Project progress work #2963 (Closed): [Installation&On-site support] Connect and field test system
- 08:41 Project progress work #2956 (Closed): [Installation&On-site support] Installation and wiring cabinet PLC (server room)
- 08:36 Project progress work #2954 (Closed): [Installation&On-site support] Hardware installation
- 08:34 Project progress work #1287: [Coding] Web application
- 1. Production Overview
2. Production Monitoring
3. 3D Facility Monitoring
4. 3D Production Monitoring
5. Alarm Lo... - 08:22 Project progress work #1287 (In Progress): [Coding] Web application