- 09:12 Project progress work #6810 (Closed): [Installation&On-site support] On line support
- 09:12 Project progress work #6810 (Closed): [Installation&On-site support] On line support
- 09:08 Project progress work #6809 (Closed): [Installation&On-site support] On-site Support Go Live
- 09:08 Project progress work #6809 (Closed): [Installation&On-site support] On-site Support Go Live
- 09:04 Project progress work #6808 (Closed): [Installation&On-site support] On-site Training
- 09:04 Project progress work #6808 (Closed): [Installation&On-site support] On-site Training
- 09:02 Project progress work #6807 (Closed): [Installation&On-site support] "Manual Update & Operation Training
- 09:02 Project progress work #6807 (Closed): [Installation&On-site support] "Manual Update & Operation Training
- 08:59 Project progress work #6806 (Closed): [Installation&On-site support] BOM data import into the WMS system.
- 08:59 Project progress work #6806 (Closed): [Installation&On-site support] BOM data import into the WMS system.
- 08:58 Project progress work #6805 (New): [Installation&On-site support]
02 Mar 2026
- 14:07 Project progress work #6773 (Closed): [Coding] Add Function to Edit Order Quantity in Purchase and Delivery Plan.
- 14:07 Project progress work #6773 (Closed): [Coding] Add Function to Edit Order Quantity in Purchase and Delivery Plan.
26 Feb 2026