Project

General

Profile

Activity

From 03 Feb 2026 to 12 Feb 2026

12 Feb 2026

15:55 Project progress work #1156 (Closed): [Installation&On-site support] Modify
Waraporn Promsopa
15:52 Project progress work #1156 (New): [Installation&On-site support] Modify
Waraporn Promsopa
15:54 Project progress work #6602 (Closed): [Installation&On-site support] Remote Deployment After Source Code Modification.
Waraporn Promsopa
15:53 Project progress work #6602 (Closed): [Installation&On-site support] Remote Deployment After Source Code Modification.
Waraporn Promsopa
15:52 Project progress work #481 (Closed): [Coding] Handy terminal stock management system for Finished product PHP web
Waraporn Promsopa
15:47 Project progress work #481 (New): [Coding] Handy terminal stock management system for Finished product PHP web
Waraporn Promsopa
15:51 Project progress work #6601 (Closed): [Coding] Add a new menu item for POKAYOKA Matching.
Waraporn Promsopa
15:50 Project progress work #6601 (Closed): [Coding] Add a new menu item for POKAYOKA Matching.
Waraporn Promsopa
15:48 Project progress work #6600 (Closed): [Coding] Add a new menu item for Inbound Inspection.
Waraporn Promsopa
15:48 Project progress work #6600 (Closed): [Coding] Add a new menu item for Inbound Inspection.
Waraporn Promsopa
11:16 Project progress work #6575 (Closed): [Installation&On-site support] Review/Verify all processes of the SKT Handy Terminal.
Waraporn Promsopa
11:16 Project progress work #6575 (Closed): [Installation&On-site support] Review/Verify all processes of the SKT Handy Terminal.
Waraporn Promsopa
 