14 Sep 2025
- 16:20 Project progress work #1438 (Closed): issue onsite 12 September 2025
- Update new Function for fixed Kanban is status don't match
generate QR code Leader by department
Test on departme...
10 Sep 2025
- 16:11 Project progress work #1390 (Closed): [Installation&on-site support] Fix new 2 issues
- Onsite install Software handy and Pegasus
- 16:09 Project progress work #1389 (Closed): [Installation&on-site support] Check web Pegasus
- Recheck code Pegasus success
- 16:08 Project progress work #1388 (Closed): [Installation&on-site support] Check program handy *Waiting for feedback
- Recheck logical handy form request Customer.
- 16:03 Project progress work #1387 (Closed): [Installation&on-site support] Check KANBAN