Activity
From 01 Nov 2024 to 10 Nov 2024
07 Nov 2024
- 11:01 4.00 hours (Project progress work #747 (Closed): Testing Modify Pegasus to Pegasus2)
- Fix bugs in the Kanban Status Management page (import function) and Stock Maintenance page (insert and update functio...
- 10:59 4.00 hours (Project progress work #747 (Closed): Testing Modify Pegasus to Pegasus2)
- Remotely install and test the system after fixing bugs and swap to web pegasus 2.
04 Nov 2024
- 12:28 4.00 hours (Project progress work #747 (Closed): Testing Modify Pegasus to Pegasus2)
- Remote swap Pegasus 2 to Pegasus 1 due to import, test case, and various report generation errors on Pegasus 2.
Also available in: Atom