Estimated time: 528.00 Spent time: 64.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
2761 Project progress work In Progress Normal [Internal Design] Nattapol Poeam 0.00 29 Oct 2025 16:06 Actions
2760 Project progress work New Normal [Requirement definition] Nattapol Poeam 0.00 29 Oct 2025 16:06 Actions
2759 Parent project In Progress Normal [PJ250074] Operation monitoring system for ShinDengen for 5units 1. Software & Hardware (PT. DJK INDONESIA) Nattapol Poeam 0.00 0.00 19 Nov 2025 15:21 Actions
3015 Parent project In Progress Normal [PJ250090] Operation monitoring system for ShinDengen Customization fee Nattapol Poeam 544.00 0.00 19 Dec 2025 10:39 Actions
2783 Parent project In Progress Normal [PJ250078] Operation monitoring system for ShinDengen 100% (DAIICHI JITSUGYO (THAILAND) CO., LTD) Nattapol Poeam 392.00 0.00 28 Nov 2025 13:15 Actions
3321 Project progress work New Normal [Coding] Validation check Signal & Information Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3320 Project progress work New Normal [Coding] WDT Configuration Line 5 Pattanasak Chaonchom 0.00 19 Dec 2025 09:22 Actions
3319 Project progress work New Normal [Coding] Validation check Signal & Information Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3318 Project progress work New Normal [Coding] WDT Configuration Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:21 Actions
3317 Project progress work New Normal [Coding] Validation check Signal & Information Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:23 Actions
3316 Project progress work New Normal [Coding] WDT Configuration Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:19 Actions
3330 Project progress work New Normal [Installation&On-site support] Software installation Pattanasak Chaonchom 40.00 0.00 19 Dec 2025 10:38 Actions
3027 Project progress work New Normal [Coding] Addition time to used and auto end Phattarapong Kammee 0.00 27 Nov 2025 17:16 Actions
3026 Project progress work New Normal [Coding] Addition plan NO OT, Plan Machine Stop, Other Phattarapong Kammee 0.00 27 Nov 2025 17:14 Actions
3025 Project progress work New Normal [Coding] Add Import/Export to File CSV Phattarapong Kammee 0.00 27 Nov 2025 17:16 Actions
821 Project progress work New Normal [Colding] Back-end Web dashboard application PHP Ronnagon Kongsuwan 0.00 28 Nov 2024 00:25 Actions
3031 Project progress work New Normal [Installation&On-site support] Software Machine data collection & Configuration Line 2 Thiraporn Amornsirinukorh 16.00 0.00 28 Nov 2025 11:57 Actions
3033 Project progress work New Normal [Installation&On-site support] Software Machine data collection & Configuration Line 3,4,5 Thiraporn Amornsirinukorh 16.00 0.00 28 Nov 2025 11:59 Actions
3024 Project progress work New Normal [Coding] Change "OEE, Plan delay time; Plan shutdown" lot by lot day per time Thiraporn Amornsirinukorh 0.00 27 Nov 2025 17:09 Actions
3023 Project progress work New Normal [Coding] Notification OEE by E-Mail or Smartwatch Thiraporn Amornsirinukorh 0.00 27 Nov 2025 17:08 Actions
3022 Project progress work New Normal [Coding] Manual to Edit Actual (Quantity and Color) Thiraporn Amornsirinukorh 0.00 27 Nov 2025 16:57 Actions
3021 Project progress work New Normal [Coding] Change color Gray for Breakdown Actual Thiraporn Amornsirinukorh 0.00 27 Nov 2025 16:53 Actions
3020 Project progress work New Normal [Coding] Add target setting Thiraporn Amornsirinukorh 0.00 27 Nov 2025 16:47 Actions
3019 Project progress work New Normal [Coding] Add Color OEE (Red, Green) Thiraporn Amornsirinukorh 0.00 27 Nov 2025 16:47 Actions
3018 Project progress work New Normal [Coding] Addition detail "Plan delay, Planned shutdown overtime, OEE" Product by product Thiraporn Amornsirinukorh 0.00 27 Nov 2025 16:45 Actions