# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
3015 Parent project In Progress Normal [PJ250090] Operation monitoring system for ShinDengen Customization fee Nattapol Poeam 544.00 0.00 19 Dec 2025 10:39 Actions
2783 Parent project In Progress Normal [PJ250078] Operation monitoring system for ShinDengen 100% (DAIICHI JITSUGYO (THAILAND) CO., LTD) Nattapol Poeam 392.00 0.00 28 Nov 2025 13:15 Actions
2763 Project progress work New Normal [Installation&On-site support] Nattapol Poeam 0.00 29 Oct 2025 16:06 Actions
2762 Project progress work New Normal [Coding] Nattapol Poeam 0.00 29 Oct 2025 16:06 Actions
2761 Project progress work In Progress Normal [Internal Design] Nattapol Poeam 0.00 29 Oct 2025 16:06 Actions
2760 Project progress work New Normal [Requirement definition] Nattapol Poeam 0.00 29 Oct 2025 16:06 Actions
2759 Parent project In Progress Normal [PJ250074] Operation monitoring system for ShinDengen for 5units 1. Software & Hardware (PT. DJK INDONESIA) Nattapol Poeam 0.00 0.00 19 Nov 2025 15:21 Actions