Project progress work #774: [Colding] Front-end Web dashboard application PHP
Project progress work #821: [Colding] Back-end Web dashboard application PHP
Parent project #2783: [PJ250078] Operation monitoring system for ShinDengen 100% (DAIICHI JITSUGYO (THAILAND) CO., LTD)

Status

New
New
In Progress
In Progress

Priority

Normal
Normal
Normal
Normal

Total estimated time

4232.00
3680.00

Total spent time

0.00
0.00
0.00

Updated

28 Nov 2024 00:24
28 Nov 2024 00:25
26 May 2026 10:14
26 May 2026 10:14
 
49
50
51
52
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Tomas Tech All Project Management
 
 
SHINDENGEN (THAILAND) CO., LTD.
New 0%
New 0%
 
 
 
 
In Progress
Parent project #2783: [PJ250078] Operation monitoring system for ShinDengen 100% (DAIICHI JITSUGYO (THAILAND) CO., LTD)

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: In Progress
Start date: 17 Nov 2025
Due date: 20 May 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
 
In Progress 100%
Project progress work #2786: [Coding]

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: In Progress
Start date: 27 Nov 2025
Due date: 20 May 2026
Assignee:
Priority: Normal
 