Project

General

Profile

For internal project work assignment report without Nozaki

« November | January 2026 »

Apply Clear

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
49

30

1

2

3

4

5

6

50

7

8

9

10

11

12

13

51

14

15

16

17

18

19

20

52

21

22

23

24

25

26

Project progress work #3350: [Installation&On-site suppo... Project progress work #3350: [Installation&On-site support] Onsite support issue and request

Project: PROSPIRA THAILAND CO., LTD.
Status: In Progress
Start date: 14 Oct 2025
Due date: 26 Dec 2025
Assignee: Phongphan Suwanteamee
Priority: Normal
Project progress work #3147: [Installation&OIn-site supp... Project progress work #3147: [Installation&OIn-site support] Onsite support

Project: PROSPIRA THAILAND CO., LTD.
Status: In Progress
Start date: 14 Oct 2025
Due date: 26 Dec 2025
Assignee: Kittikun Chunhachotwanit
Priority: Normal
Project progress work #1174: [Installation&On-site support] Project progress work #1174: [Installation&On-site support]

Project: PROSPIRA THAILAND CO., LTD.
Status: In Progress
Start date: 14 Oct 2025
Due date: 26 Dec 2025
Assignee: Priroj Neamjarn
Priority: Normal
Parent project #1009: [PJ250020] Warehouse manage... Parent project #1009: [PJ250020] Warehouse management system ( Prospira (Thailand) Co., Ltd. )

Project: PROSPIRA THAILAND CO., LTD.
Status: In Progress
Start date: 09 Dec 2024
Due date: 26 Dec 2025
Assignee: Anek Sanohkham
Priority: Normal

27

1

28

29

30

31

1

2

3

issue beginning this day issue ending this day issue beginning and ending this day