Activity
From 23 Aug 2025 to 01 Sep 2025
01 Sep 2025
- 16:54 Project progress work #1010: Warehouse management system
- Go live
-support 2 weeks
29 Aug 2025
- 16:45 Project progress work #1010: Warehouse management system
- today
-Support on site
27 Aug 2025
- 17:14 Project progress work #1010: Warehouse management system
- today
-Master data view (7 items)
tomorrow
-Master data view (7 items)
26 Aug 2025
- 23:29 Project progress work #1010: Warehouse management system
- today
-ON site support
tomorrow
-Fix issue
25 Aug 2025
- 20:37 Project progress work #1010: Warehouse management system
- today
-View data for dashboard
tomorrow
-ON site support
23 Aug 2025
- 17:03 Project progress work #1010: Warehouse management system
- today
-Change fifo search lot for compund tag
-Receive split part on pallet
tomorrow
-Master data
-View data fo...
Also available in: Atom