Activity
From 24 Jul 2025 to 02 Aug 2025
01 Aug 2025
- 17:32 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
- 17:32 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
31 Jul 2025
- 17:12 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Training and update application on site
- 17:12 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Training and update application on site
30 Jul 2025
- 17:24 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
- 17:24 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
29 Jul 2025
- 17:01 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
- 17:01 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
26 Jul 2025
- 17:15 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
- 17:15 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Fix and make new requirement
25 Jul 2025
- 16:41 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Training on site FG process
- 16:41 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Training on site FG process
24 Jul 2025
- 21:30 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Adjust Process FG Inbound (QA, FG Inbound, SO Outbound)
- 21:29 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
- -Adjust Process FG Inbound (QA, FG Inbound, SO Outbound)
Also available in: Atom