11 Jul 2025

17:45 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-fix issue SIMP Inbound -Stock Check -Change Location Priroj Neamjarn
17:45 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-fix issue SIMP Inbound -Stock Check -Change Location Priroj Neamjarn

09 Jul 2025

16:32 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-fix issue RM-inbound, MO Request outbound -Make manual RM-inbound, MO Request outbound Priroj Neamjarn
16:32 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-fix issue RM-inbound, MO Request outbound -Make manual RM-inbound, MO Request outbound Priroj Neamjarn

08 Jul 2025

17:17 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Stock Priroj Neamjarn
17:12 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Stock Priroj Neamjarn

07 Jul 2025

17:10 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Fix issue Inbound Process (First training) -MO Outbound Process -SO Outbound Process Priroj Neamjarn
17:10 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Fix issue Inbound Process (First training) -MO Outbound Process -SO Outbound Process Priroj Neamjarn

04 Jul 2025

17:09 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Fix issue Inbound Process (First training) -MO Outbound Process -SO Outbound Process Priroj Neamjarn
17:09 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Fix issue Inbound Process (First training) -MO Outbound Process -SO Outbound Process Priroj Neamjarn

03 Jul 2025

17:21 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-MO Outbound Process -SO Outbound Process -Support customer test inbound process Priroj Neamjarn
17:21 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-MO Outbound Process -SO Outbound Process -Support customer test inbound process Priroj Neamjarn

02 Jul 2025

17:18 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-MO Outbound Process -Install Handy API to PSTH Priroj Neamjarn
17:18 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-MO Outbound Process -Install Handy API to PSTH Priroj Neamjarn
 