17 Sep 2024

16:20 8.00 hours (Project progress work #679 (Closed): Power meter monitoring)
Test and Deploy to server Priroj Neamjarn
16:20 8.00 hours (Project progress work #679 (Closed): Power meter monitoring)
Deploy to server Priroj Neamjarn

16 Sep 2024

16:46 8.00 hours (Project progress work #596 (Closed): [Requirement and support] Infrastructure IoT system for OTICS(Thailand))
Meeting Nattapol Poeam
16:42 8.00 hours (Project progress work #679 (Closed): Power meter monitoring)
Include rate to function for calculate in system. Priroj Neamjarn
16:42 8.00 hours (Project progress work #679 (Closed): Power meter monitoring)
Include rate to function for calculate in system. Priroj Neamjarn
16:31 8.00 hours (Project progress work #645 (Closed): [ Installation&On-site support ] Power meter monitoring system for OTICS)
Install and debug program Nattapol Poeam
16:31 8.00 hours (Project progress work #645 (Closed): [ Installation&On-site support ] Power meter monitoring system for OTICS)
Installation Nattapol Poeam
16:30 8.00 hours (Project progress work #688 (Closed): [ Task ] Coding C# Transfer data PLC to DB)
Program developer Nattapol Poeam
16:30 8.00 hours (Project progress work #688 (Closed): [ Task ] Coding C# Transfer data PLC to DB)
Program developer Nattapol Poeam
16:25 8.00 hours (Project progress work #688 (Closed): [ Task ] Coding C# Transfer data PLC to DB)
Program developer Nattapol Poeam
16:25 8.00 hours (Project progress work #688 (Closed): [ Task ] Coding C# Transfer data PLC to DB)
Program developer Nattapol Poeam
 