Activity
From 23 Aug 2024 to 01 Sep 2024
29 Aug 2024
- 14:09 8.00 hours (Project progress work #703 (Closed): Make The User Manual)
- 14:09 8.00 hours (Project progress work #703 (Closed): Make The User Manual)
- 14:02 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 14:02 8.00 hours (Project progress work #675 (Closed): Program Testing)
27 Aug 2024
- 16:51 16.00 hours (Project progress work #503 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PHP)
- Setup a remote dashboard
- 08:16 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 08:16 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 08:16 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 08:16 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 08:16 8.00 hours (Project progress work #675 (Closed): Program Testing)
26 Aug 2024
- 16:59 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:59 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:59 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:59 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:59 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:59 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:58 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:58 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:58 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:57 8.00 hours (Project progress work #675 (Closed): Program Testing)
- 16:57 8.00 hours (Project progress work #675 (Closed): Program Testing)
24 Aug 2024
- 16:24 8.00 hours (Project progress work #645 (Closed): [ Installation&On-site support ] Power meter monitoring system for OTICS)
- installation
23 Aug 2024
Also available in: Atom