12 Jul 2024
- 16:07 8.00 hours (Project progress work #636 (Closed): Electrical drawing design)
- PR Electrical part list
- 15:53 8.00 hours (Project progress work #636 (Closed): Electrical drawing design)
- PR Electrical part list
- 15:46 8.00 hours (Project progress work #636 (Closed): Electrical drawing design)
- PR Electrical part list
- 15:45 8.00 hours (Project progress work #636 (Closed): Electrical drawing design)
- PR Electrical part list
- 15:42 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- 15:41 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- 15:41 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- 15:41 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- 15:41 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- programming PLC
- 15:40 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- programming PLC