Activity
From 03 Jun 2024 to 12 Jun 2024
12 Jun 2024
- 16:46 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- Data Buffer Design and PLC Programming
- 16:46 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- Data Buffer Design
- 16:39 8.00 hours (Project progress work #636 (Closed): Electrical drawing design)
05 Jun 2024
- 16:09 4.00 hours (Project progress work #596 (Closed): [Requirement and support] Infrastructure IoT system for OTICS(Thailand))
- Meeting about expain concept specification
- 16:00 4.00 hours (Project progress work #596 (Closed): [Requirement and support] Infrastructure IoT system for OTICS(Thailand))
- Kick off meeting
- 11:14 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- Data Mapping
- 11:14 8.00 hours (Project progress work #502 (Closed): [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence)
- Data Mapping
Also available in: Atom